Dredging

Itajaí-Mirim plan widens the channel and adds two flood-control gates

Published 19 July 2026 Editorial responsibility IMWO Region Americas Confidence Confirmed
Close view of an Itajaí-Mirim river-improvement plan and map during a June 2026 municipal and state Civil Defense meeting

Municipality of Itajaí; June 2026 programme discussion, not construction evidence

Santa Catarina's P508221 programme defines widening and deepening of the rectified Itajaí-Mirim channel, desilting part of the old river and two flood-control gates. P508221 is Active and Board Approved in the World Bank portfolio; the April 2026 procurement plan omits the main river works package.

What changed

The World Bank project API establishes Active and Board Approved status, the USD 119.2 million current IBRD commitment and the 31 August 2033 financial closing date. The release establishes the high-level physical scope. The state PEPI defines the river reaches, channel widening, desilting and two gates. The April procurement plan does not list the main works package. Itajaí's May technical-services contract covers design preparation for a natural-river reach, while its 18 June meeting records programme discussion with state Civil Defense and the World Bank. Neither municipal record is P508221 construction mobilisation.

Why it matters

The PEPI fixes the geography before the commercial package is public. Rectified-channel work runs from KM 12 to the Itajaí-Açu mouth, while old-river work runs from Itaipava to the channel confluence. The sediment route, gate split, package value and acceptance basis remain open.

Decision read

What remains open

This is an approved waterworks programme, not an active construction claim. Procurement becomes actionable when an updated STEP plan or state tender joins the river reach, design surface, sediment classification, gate civils, environmental conditions and bid timetable. Port-access dredging in the neighboring Itajaí-Açu must remain a separate record.

Next watchpoints

  • Main works procurement entry
  • Final channel geometry and design surface
  • Sediment testing and material route
  • Bank reinforcement and urban access
  • Flood-control gate package split
  • Environmental licence and mitigation plans
  • Pre-dredge survey and notice to proceed
  • Post-work survey and gate acceptance

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Sources used 6

Corrections and methodology

Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.

Review methodology Open intelligence archive Submit a correction