Dredging Progress

Progreso Receives the Dredger for Third-Phase Stage One

Published 3 November 2026 Publisher IMWO Region Americas Confidence Confirmed
A new stage starts with a survey baseline. Progreso / third phase, stage 1 / 26 October 2026.

IMWO original engineering diagram; source: ASIPONA Progreso

ASIPONA Progreso records Fernando de Magallanes arriving for the first stage of the expansion's third phase. Its 26 October release gives an estimated 3,076,370 m3 dredging scope for this new stage.

The owner records a new dredger mobilisation

ASIPONA Progreso's 26 October release 34/2026 reports the arrival of Fernando de Magallanes to begin third-phase stage 1 of the port expansion. The owner gives an estimated 3,076,370 m3 of dredging for the stage. This adds a field mobilisation record after the programme's earlier state-financed channel work and separate private berth stage. The July north-platform tender outcome remains part of the procurement history; the October release identifies the new phase and quantity [1].

The stage quantity needs its own survey baseline

A dredger returning to a multi-stage port project needs a defined handover from the earlier excavation. The new stage should have its own survey surface, cut limits and material-handling arrangement, with completed predecessor work identified in the same reference system. That prevents earlier excavation from being carried into the new production account. The owner's estimated volume provides the scale for planning plant time; measured progress will depend on the accepted starting surface and the final excavation geometry.

Evidence conclusion

Follow the new stage through its delivery records

The third-phase stage 1 campaign needs its own starting survey, excavation limits and material-receiving programme. ASIPONA's arrival account identifies a vessel and an estimated scope, which support mobilisation planning. Production and acceptance depend on subsequent survey quantities and agreed surfaces. The earlier 40 ha platform tender, recorded void in July, retains its own procurement history [2,3]. Its quantities and commercial conditions require reconciliation with the operative stage 1 package before they enter a current estimate.

Outstanding evidence

  • Third-phase stage 1 contract scope and material destination
  • Starting survey, cut limits and stage-specific measured progress
  • Acceptance geometry and interfaces with earlier channel and berth works