Hydrographic Practice
Skipanon clamshell campaign has a dated survey baseline
IMWO original skipanon engineering diagram from the cited primary records
USACE lists Skipanon clamshell dredging from 25 October with Sea Horse and Robert L. The 2 September entrance survey supplies a dated MLLW baseline for tracking bed changes.
The September chart states its own depth reference
Portland District's 2 September survey shows the entrance and the bend towards Warrenton. Its notes give soundings in feet below Mean Lower Low Water and describe the existing project as maintained at 16 ft based on user needs. The chart represents conditions on its survey date. Its register supplies the PDF, XYZ data and shape files for the same survey.
The scow cycle affects digging time
Clamshell excavation transfers material into a scow, so continuous digging depends on loading capacity, scow availability and the permitted placement journey. The current plant listing establishes the named equipment; it gives no cycle time or completed quantity. For campaign control, the daily record should link dredge position and loading hours to scow departures, returns and placement records. That makes a transport interruption visible alongside any limitation at the digging face.
Evidence conclusion
Progress surveys need the same datum and reach
A follow-up survey should be compared with the September baseline using consistent horizontal references, vertical datum and channel limits. The 16 ft project note provides context for the maintained channel, while the September soundings show the bed that existed before this listed start. Acceptance depends on the applicable contract template and final survey. The published XYZ and shape files support comparison of matching reaches, coordinates and survey dates.
Outstanding evidence
- Current contract template and permitted placement route
- Loading hours, scow cycles and placement receipts
- Dated progress/final surveys with matching datum and limits
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
- Active jobs: FY26 OR/WA Clamshell, Skipanon USACE DQM, Observed 28 October 2026; start listed 25 October
- Active plant: Sea Horse and Robert L USACE DQM, Observed 28 October 2026
-
Skipanon Channel entrance survey CM_09_SKP_20260902_CS
USACE Portland District, 2 September 2026
Complete original one-page PDF obtained; map, legend, project and datum notes viewed.
- Portland District hydrographic survey register USACE Portland District, Accessed 28 October 2026