Pontoon contract evidence

Swansea signs two pontoons after its original delivery window slips

Published 8 August 2026 Publisher IMWO Region Europe Confidence Confirmed
Completed River Tawe floating pontoon and gangway from Inland and Coastal Marina Systems' separate 2023 Swansea installation

Inland and Coastal Marina Systems; exact 2023 River Tawe predecessor installation, not the 2026 Morfa Quay and New Cut Road works or current progress

Swansea signed Inland and Coastal Marina Systems UK Ltd for two River Tawe pontoons at GBP 411,775.70 excluding VAT. The current 20 July to 2 October 2026 period replaces a February-to-April tender window, but neither the award notice nor available owner and contractor pages prove fabrication, site possession or installation at Morfa Quay or New Cut Road.

The 15 July signature resets supplier, price and delivery dates

Find a Tender controls the supplier, signature, signed values and contract period. Swansea Council controls the two-pontoon programme context. The image is from Inland and Coastal's separate November 2023 River Tawe project and is labelled as predecessor evidence, not current progress.

The contract is active while both physical sites remain unverified

A two-location pontoon package concentrates design, fabrication and installation responsibility in one specialist contractor, but each site still has its own survey, shore connection, restraint or anchoring, access, tidal, navigation and commissioning risks. An administrative start date says nothing about whether either pontoon is fabricated, afloat, fixed or accepted.

Evidence conclusion

Award value, tender estimate and predecessor evidence have distinct roles

The signed GBP 411,775.70 excluding-VAT value is distinct from the earlier GBP 449,999 estimate, and the GBP 494,130.84 including-VAT value must not be mixed with either. Inland and Coastal's documented 2023 River Tawe installation establishes contractor-specific local delivery precedent and provides an exact system photograph. It is not one of the two 2026 sites and cannot establish current progress. A site-specific fabrication, installation or commissioning record is required to advance the delivery status.

Outstanding evidence

  • Site possession and accepted programme at both locations
  • Approved pontoon, gangway, restraint and shore-interface design
  • Fabrication release, transport and lifting or launching method
  • Morfa Quay and New Cut Road installation evidence
  • Named lower tiers and package values
  • Commissioning, owner acceptance, variations and final value

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Sources used 5