Woodman Point's AUD 17.34 million ceiling is not its released base scope
Transport WA; final-design visualization, not construction-progress evidence
Advanteering Civil Engineers has completed detailed design and started early off-site construction for the new Woodman Point Ammo Jetty. The owner describes an initial AUD 11.67 million main-jetty and T-head award with provision up to AUD 17.3 million including landside works, while Tenders WA records an exact AUD 17,342,374 contract value.
Off-site delivery is confirmed before on-site mobilisation
Transport WA controls the design and off-site status, project scope and planned onsite timing. The WA Government release controls the AUD 11.67 million initial award and up-to-AUD 17.3 million provision. Tenders WA controls the exact AUD 17,342,374 value and contract period. No on-site start or subcontract record has been located.
Value and progress each need two-layer evidence
The two values describe different commercial boundaries. The lower figure is the initial released marine scope; the higher figure is the recorded contract envelope. Presenting AUD 17.34 million as fully released physical work would overstate the current package. Likewise, early off-site construction is meaningful progress but does not prove demolition or piling has begun at Woodman Point.
Evidence conclusion
Watch option release and first on-site evidence separately
A landside option release would define how much of the contract ceiling becomes active scope. A dated on-site start would move the physical status beyond off-site fabrication. Once mobilisation occurs, project-level records must identify demolition sequencing around retained 1939 piles, fabrication and marine-plant allocation, then owner inspection and reopening. No lower-tier suppliers are yet public.
Outstanding evidence
- Landside option release within the AUD 17.34 million ceiling
- Dated on-site mobilisation and marine safety notice
- Demolition and retained-pile method
- T-head, deck and access-platform fabrication
- Marine plant, lifting, diving and electrical subcontractors
- Owner acceptance and public reopening
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 3
- DOT413022 contract award Tenders WA, Awarded 28 April 2026; checked 5 August 2026
- New Woodman Point Ammo Jetty Transport WA, Updated 16 June 2026
- Work to start on new Woodman Point Ammo Jetty Government of Western Australia, 21 May 2026