Marine Contracting
Woodman Point has mobilised under a two-asset WA marine contract
Transport WA; official Jetty 1 scope image, not construction-progress evidence
Jetty and Marine Constructions holds the AUD 4,868,726 DOT411425 contract for two independent marine renewals: Woodman Point's four-lane western boat ramp and Fremantle Fishing Boat Harbour's Jetty 1. A Transport WA marine notice confirms Woodman Point operations from 27 July 2026, but the Fremantle project page has not published an equivalent dated mobilisation event.
Notice 6933 places marine plant at Woodman Point only
Tenders WA records the award and value, while Transport WA project pages define the two asset scopes. Marine Notice 6933 documents field activity at Woodman Point only. The owner describes a combined design-and-construct package; no cited source discloses a price split, subcontractors or dated Jetty 1 mobilisation.
Only Woodman Point has dated field activity
Notice 6933 identifies a spudded barge, tug, crane, support vessels and possible divers at Woodman Point from 27 July 2026. It does not cover Fremantle Jetty 1, and the AUD 4,868,726 award provides no site-by-site price split. Woodman Point field activity therefore cannot be used as evidence of Jetty 1 mobilisation or progress.
Evidence conclusion
Fremantle Jetty 1 remains without a dated mobilisation record
The shared award and both scopes are confirmed. Notice 6933 establishes Woodman Point field activity from 27 July 2026, while no equivalent closure, marine notice or site record has been published for Jetty 1. Demolition, fabrication, installation, testing and acceptance remain separate for each asset, and the owner's 2027 target does not establish a combined handover.
Outstanding evidence
- Fremantle Jetty 1 closure and field-mobilisation notice
- Site-by-site contract price and scope allocation
- Pile, pontoon, fabrication and demolition subcontractors
- Woodman Point ramp and holding-jetty installation
- Jetty 1 floating-pen installation and service connections
- Owner acceptance and reopening documentation
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- DOT411425 contract award Tenders WA, Awarded 9 March 2026; checked 5 August 2026
- Fremantle Fishing Boat Harbour projects - Jetty 1 replacement Transport WA, Updated 8 July 2026
- Woodman Point Boating Precinct Transport WA, Updated 18 March 2026
- Temporary Notice to Mariners 6933 Transport WA, Issued 17 July 2026
- Major marine upgrades at Fremantle and Woodman Point Government of Western Australia, 18 March 2026