Procurement

Aqaba Oil Berth Tender Divides Marine and Operating Scope

Published 31 October 2026 Publisher IMWO Region Middle East Confidence Confirmed
Aqaba conceptual interface connects marine EPC structures with the parallel equipment-and-operation package and the topside design inputs crossing that boundary.

IMWO original engineering diagram; source: Aqaba Development Corporation

ADC's new oil-berth invitation combines marine EPC works with topside engineering, alongside a parallel operator procurement. Pipeline tie-ins and the equipment handover need particular attention before bidders freeze their scope.

A new berth connects to existing oil and LPG systems

Aqaba Development Corporation's 7 October invitation for tender 90/A/2026 covers marine EPC works for a new oil berth south of the existing oil jetty and north of the LNG terminal. The stated vessel range is 3,000-160,000 DWT. Marine components include a loading platform, berthing and mooring dolphins, trestle and causeway. Topside engineering includes piping, the pipeline corridor, trestle pipe racks, a bridge over a wadi and tie-ins to existing pump stations and oil/LPG lines. [1] ADC's project description provides a parallel Equip, Operate and Transfer procurement for the terminal operator. [2]

Equipment loads have to enter the marine design early

The loading platform and pipe supports need the weights, operating movements and maintenance access of the equipment they carry. Pipeline design also has to resolve support reactions, thermal movement, tie-in conditions and the sequence for connecting to existing facilities. Parallel marine and operator procurement creates a timing problem if those equipment inputs arrive after structural design or fabrication. A bid interface schedule should identify who supplies each load and connection datum, when it is frozen, and which items remain provisional. That schedule supports the engineering offer while the procurement documents establish supply, installation and contractual responsibility.

Evidence conclusion

Document access and the bid deadline are different dates

The invitation sets 16 December 2026, before 12:00 Jordan time, for technical and financial bids, but its document-request deadline was 28 October. It requires a joint venture combining an international marine specialist with a Jordanian Grade One (A) civil contractor. The tender security is JOD 600,000. [1] A firm approaching the opportunity now needs ADC to confirm access and participation before treating the future bid date as an entry window. The advertised contract basis is the 1999 FIDIC Silver Book. Package-specific requirements will determine the marine handover, equipment interface and testing obligations. For firms already holding the documents, the immediate engineering task is to reconcile the topside inputs with the operator package and the existing terminal's connection constraints.

Outstanding evidence

  • ADC confirmation of document access after the 28 October cutoff
  • Equipment loads, connection data and marine/operator scope schedule
  • Current clarifications, JV conditions, security and December bid instructions