Mooring Supply Chain
Pearl Harbor's two-buoy order now has a visible subcontract chain
Oceanetics Inc. holds U.S. Navy delivery order N3943025F0149 to install two mooring buoys at Wharf V5, Joint Base Pearl Harbor-Hickam. USAspending reports USD 1,377,977 through 11 September 2026 and identifies two subawards: USD 746,755.50 to Healy Tibbitts Builders for a project charter agreement and USD 124,112 to Marine Fenders International for an Ocean Guard mooring buoy. These records expose part of the delivery chain, but not field installation or acceptance.
Two subawards turn a prime-only record into a package map
USAspending controls the prime and subaward identities, dates, values and descriptions. The Navy objective explicitly places the package at Wharf V5 in Pearl Harbor; a conflicting Annapolis place field is treated as metadata noise. Oceanetics, Marine Fenders and Healy Tibbitts pages establish capabilities only. No cited source confirms mobilisation, buoy delivery acceptance, anchor placement, installation, testing, handover or operational use. The image shows a separate 2013 Pearl Harbor fleet-mooring inspection and is contextual, not current Wharf V5 evidence.
Named firms are only the first layer
A prime award alone says who owns delivery. The two subawards begin to show how that obligation is being assembled: charter support and buoy supply. Their exact descriptions are commercially specific but narrow. A charter agreement is not proof that Healy Tibbitts owns installation, and an Ocean Guard line item does not reveal model, geometry, working load, fittings, testing or accepted quantity.
Evidence conclusion
Installation, testing and acceptance remain unconfirmed
The engineering and execution chain remains materially open. Anchor blocks, chain and ground tackle, mooring analysis, survey, lifting, diving, positioning, temporary navigation controls, inspection, load verification and Navy acceptance are not allocated in published task-order or subaward data. Company capability pages do not assign those project-specific roles. A status advance requires dated mobilisation, delivery, installation, test or acceptance evidence.
Outstanding evidence
- Oceanetics mobilisation and installation spread
- Healy Tibbitts chartered vessel and exact support scope
- Marine Fenders buoy model, fittings and accepted delivery
- Ground tackle, survey, lift, dive and positioning packages
- Testing, Navy acceptance and first operational vessel use
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 6
- N3943025F0149 Wharf V5 mooring-buoy installation award USAspending.gov, Awarded 9 September 2025; reviewed 5 August 2026
- N3943025F0149 prime-award API record USAspending.gov, Current API record reviewed 5 August 2026
- Moorings Oceanetics, Current capability page reviewed 5 August 2026
- Ocean Guard mooring buoys Marine Fenders International, Current product page reviewed 5 August 2026
- About Healy Tibbitts Builders Healy Tibbitts Builders, Current capability page reviewed 5 August 2026
- Fleet mooring inspections U.S. Navy via DVIDS, 26 September 2013