Capital dredging

Boskalis selected for Southampton channel deepening

Published 18 July 2026 Updated 15 October 2026 Publisher IMWO Region Europe Confidence Confirmed
Boskalis backhoe dredger Magnor loading an attendant barge during Southampton's separate 2024 Western Docks channel-widening project

Associated British Ports; 2024 Southampton widening context

ABP selected Boskalis Westminster on 11 August 2026 for Southampton Channel Deepening. The 12 August UK6 retains a pending award, with signature unconfirmed in the complete history reviewed on 15 October. MMO's application for about 5.5 million m3 across SCT 5 and the main and Nab channels shows Submitted / (In progress) / [On Hold].

Published scope and current milestone

The official UK6 and complete procurement history identify Boskalis, the pending award and scheduled dates. MMO's visible case summary, reviewed on 15 October, supplies the current status, proposed quantities, maximum 1.3 m local cut and work windows; the hold reason and duration are unstated. The July consultation has closed. Full application attachments and an issued licence have not been reviewed. ABP's port page was reviewed in July and recorded an existing SCT 5 depth of 16.5 m. The Magnor lead image documents the separate 2024 widening works.

Dredging quantity and delivery implications

The proposed dredge extends from a live container berth through the navigation channels to the Nab approach. It combines buried pipelines, quay-wall proximity, UXO controls, sea disposal and vessel traffic with a proposed December 2026-July 2027 programme. SCT 5 would reach 17.1 m below Chart Datum and channel levels 14.0-15.2 m. Upstream work is scheduled to end by 14 March to avoid the later salmonid migration windows. ABP's completed 900,000 m3 Western Docks widening remains a separate 2024 project.

Evidence conclusion

Survey, placement and acceptance evidence

Supplier selection, signature, marine consent and physical commencement have distinct evidence requirements. The UK6 schedules signature for 30 August and a contract period from 1 September 2026 to 31 July 2027; contract execution remains unconfirmed. Its GBP 0 net and gross fields leave a usable price unconfirmed. MMO has no current consultation for the on-hold application. The application volume, including side slopes and a 0.5 m over-dredge allowance, retains its proposed basis; accepted depths require post-dredge hydrography.

Outstanding evidence

  • MMO on-hold application, licence decision and conditions
  • Signed Boskalis contract or contract-details notice
  • Final contract value, scope, programme and risk allocation
  • Ground model, UXO plan, pipeline controls and selected dredging plant
  • Sea-disposal route, environmental windows and live-port sequencing
  • Post-dredge surveys confirming SCT 5 and channel depths