Waterways
Wheeler's short window overlaps a longer Southwest Pass programme
USACE has scheduled the government hopper Wheeler for approximately 4-15 September around Head of Passes. A separate notice for Glenn Edwards covers the same river-mile envelopes but runs to approximately 31 October, making vessel-specific dates and passing arrangements important.
Two notices identify different vessel windows
The New Orleans District's 3 September notice names Wheeler between Head of Passes and approximately 22 miles Below Head of Passes in Southwest Pass, and between Head of Passes and approximately 13 miles Above Head of Passes in the Mississippi River. Its 1 September Bulletin 26-85 names the government-contract hopper Glenn Edwards in the same envelopes, starting on or about 4 September and continuing through approximately 31 October. Both describe planned 24-hour, seven-day operations. Their shared area does not make their schedules interchangeable.
Two work areas share the Head of Passes reference
Above and Below Head of Passes refer to opposite sides of the mile-zero reference. Adding 13 and 22 produces a misleading impression of a continuous 35-mile dredging contract: the notices identify areas where each vessel may work, not an excavated length or a measured output. Neither notice gives cut quantities, material-placement locations, accepted depths or a complete navigation closure.
Evidence conclusion
Passing coordination is separate from channel acceptance
Both notices ask mariners to contact dredge personnel on VHF 16 or 67 for passing arrangements, then transit cautiously at the slowest safe speed to minimise wake. Those instructions describe coordination with working plant rather than a blanket prohibition on traffic. The planned windows overlap, but do not confirm simultaneous vessel positions, completed shifts or actual mobilisation. USACE's 2015 Marine Design Center account identifies Wheeler as owned and operated by the New Orleans District and describes its earlier repowering. That history explains the government-vessel identity; it is not a new commercial award or evidence of present vessel performance. The 2017 district survey-information bulletin separately explains that bathymetric results represent conditions at their survey date and can change with dredging, shoaling and scour. Programme dates therefore cannot substitute for dated channel-condition information. For vessel operators and marine suppliers, passing coordination requires identifying which dredge is present, where it is working and which notice applies to the intended transit. Updated operational notices and current navigation advice remain the appropriate basis for a passage decision; this explanatory diagram is not a navigation chart.
Outstanding evidence
- Vessel-specific operational notices and changes to the approximate work windows
- Actual work locations and dredge passing arrangements before a transit
- Dated channel-condition surveys, distinct from scheduled dredging activity
- Published production, placement and close-out information for each campaign
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
-
Notice 214994: Wheeler in Mississippi River and Southwest Pass, printed local number MNV 26-86
U.S. Army Corps of Engineers, New Orleans District, 3 September 2026
Scheduled approximate 4-15 September work, two river-mile envelopes and passing arrangements; not observed mobilisation or accepted quantity.
-
Navigation Bulletin 26-85: Glenn Edwards in Mississippi River and Southwest Pass
U.S. Army Corps of Engineers, New Orleans District, 1 September 2026
Separate government-contract hopper notice schedules approximately 4 September-31 October; no contractor company or new award amount stated.
-
Dredge Wheeler repowered: ownership, operation and historical technical particulars
U.S. Army Corps of Engineers, Marine Design Center, 9 July 2015
Historical background on the New Orleans government vessel and 2012-2013 repowering; no 2026 output or condition inferred.
-
Navigation Bulletin 17-31: hydrographic survey information and limitations
U.S. Army Corps of Engineers, New Orleans District, 9 May 2017
Periodic survey information supports channel maintenance; results describe conditions on the indicated survey date and may change. Not a September 2026 campaign acceptance survey.