Format
Global delivery monitor
Global delivery monitor
Twenty-four current dredging and navigable-waterway records cover open and closed tenders, post-bid evaluation, procurement resets, owner-defined campaigns, awards, concession transfers, active works and one completed capital-deepening project across Africa, the Americas, Europe, Asia Pacific and the Middle East.
Public web report / version 3.7 / published 13 July 2026 / data cutoff 20 July 2026.
Evidence scope
Twenty-four public IMWO project records in Africa, the Americas, Europe, Asia Pacific and the Middle East span port access, energy-terminal access, capital deepening, recurring maintenance dredging, post-bid evaluation, procurement resets, offshore reclamation, terminal-basin formation, breakwater and revetment delivery, lifecycle channel concessions, sediment research, channel resilience, climate adaptation, multimodal canal delivery and completed deep-draft access works.
Portfolio composition
Calculated from 24 public project records in this edition. Counts describe the current portfolio, not market size, expenditure, or completion progress.
Global delivery monitor
Port and waterway owners, dredging contractors, consultants, equipment and survey specialists, environmental teams, lenders, and institutions comparing current delivery signals across international markets.
Open web and PDF report. No registration or access request is required.
Download report PDFDownload the fixed project evidence set used for this edition, including phase, confidence, update date, and primary source fields.
Download report CSVPublication record
International Marine Work Organization (2026). Global Dredging & Waterway Delivery Monitor: July 2026 (Version 3.7, IMWO-REP-2026-07-DREDGING; data cutoff 20 July 2026). https://imwo.org/reports/report-global-dredging-waterway-monitor
Calculated snapshot
Every count uses the same twenty-four-record denominator at the stated data cutoff. Bars describe the composition of the included evidence set, not global market share, forecast demand, or contractor capacity.
All twenty-four records satisfy the report's named-project, marine-scope, source, and confidence requirements.
24 of 24 included recordsSix records are at award, including Cleveland and Georgetown where planned or expected starts remain bounded from physical mobilisation.
6 of 24 included recordsArgentina's VNT and Brazil's Paranaguá contracts are signed while their scheduled August mobilisation or operating-transfer evidence remains open.
2 of 24 included recordsNew Haven has closed for bids; New York and New Jersey marine terminals are in post-bid evaluation; Richmond, Mumbai and Vadhvan remain in live procurement; and Progreso's 40 ha federal north-platform package is a procurement reset after its void ruling.
6 of 24 included recordsValencia, Bujumbura, Gothenburg, St. Joseph, Port Mansfield, Ruwais LNG and Cotonou Terminal 5 provide current field or construction evidence; accepted marine completion remains project-specific.
7 of 24 included recordsMadagascar has financing and a revised procurement plan but no main marine contract. Port Douglas has a defined maintenance scope and schedule but no published contractor or mobilisation evidence.
2 of 24 included recordsKamarajar Phase VI is officially reported complete, while survey, close-out and first deep-draft call evidence remain open.
1 of 24 included recordsThe twenty-four dredging and waterway records run from owner-defined campaigns, post-bid evaluation, tender resets and awards through active delivery, signed concessions and a completed capital-deepening contract.
Progreso now has three delivery clocks: an initial state-financed dredging phase recorded complete, a separate SSA Marine Mexico berth stage announced active, and a federal 40 ha north-platform construction-dredging tender declared void. The void tender's channel, basin, rock, material-transport, platform and sediment-control scope defines a possible future package, not a current contractor or mobilisation. The federal package can advance only through a replacement route, revised estimate, bidder list, award and notice to proceed. The macro MXN 7.225 billion programme estimate and MXN 948 million private-stage investment are not substitute values for a future federal contract.
Kamarajar's procurement trail begins with a 13.23 million cubic metre, INR 5.492 billion feasibility estimate. The February 2024 tender carried an INR 3.8 billion value and 540-day period; the October award was INR 4.407 billion excluding GST; and the December foundation release described an INR 5.45 billion investment. These are different source-stage baselines, not a final cost series. The July 2026 government release records the work complete, with 23.0-metre and 22.0-metre channel depths and an 18.0-metre operating draft, but final quantity, material route, accepted survey, completion certificate, final account and first fully laden Capesize call remain unpublished.
Six records remain at award, while Argentina's VNT and Brazil's Paranaguá have advanced through signed concessions without evidencing their scheduled August physical mobilisation or operating transfer. Paranaguá also shows why transfer is not deepening: the current PPCC portal publishes a 13.3-metre operating draft against a 15.5-metre target, and the separate pre-handover Vox Amalia campaign cannot be carried into concession performance. Georgetown makes the same timing boundary explicit for a works award. Procurement, signature, and transfer milestones are comparable, but fleet needs, tariff exposure, environmental controls, survey baselines, acceptance gates, and revenue structures are not.
Valencia adds a construction-stage terminal-basin case with about 25 million cubic metres of dredged material identified for reuse where feasible. The Port Authority's main-works contract covers quay, ancillary-quay, deepening, reclamation and demolition interfaces, while TIL's separate concession carries terminal systems and operations. The 2022 design estimate, 2023 procurement ceiling, 2024 award, Q4 physical start, 50-year concession, dredging output, accepted platform, automation and first commercial service are therefore separate records. The 137-hectare EIB reclamation definition and 126-hectare ACCIONA paved-area definition also measure different scope boundaries.
Vadhvan adds a distinct procurement-stage case. The nearshore reclamation EPC package is awarded, while the current owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July 2026 and the Daman investigation closing on 15 July. The reviewed official record contains no AOC for either package or for the breakwater. Proposed depths, areas, deadlines and the 3-plus-2-plus-10-year commercial structure are tender requirements, not contractor, mobilisation or accepted-output evidence.
Mumbai's INR 281.70 crore E.47/2026 estimate covers three campaigns, each with a 24-week completion clock and 45-day TSHD mobilisation requirement. The INR 65 crore 2026-27 budget line is an annual accounting provision, while the INR 216.40 crore E.47/2023 award and earlier Van Oord packages are history. Assured-depth lump sums, measured in-situ work, supplementary near-wall plant, non-exclusive DS1 access, VTS controls, and post-dredge surveys must therefore be read cycle by cycle rather than collapsed into one value or completion claim.
Donjon's USD 51.424 million preliminary total leads Jay Cashman by USD 3.0072 million and Posillico by USD 17.074 million. MFP-364.003 still depends on engineer-issued work orders across four terminal systems, while the contractor must select the upland placement facility and satisfy receiving-state criteria. Bid rank, award, executed value, sediment route, measured quantity and accepted work therefore remain separate records.
Tunisia moved from a second single-lot open tender to a signed main-works contract and a separate supervision procurement, but execution still divides into three different material systems. Argentina uses a lifecycle concession. Luleå reached a signed seasonal capital-works package only after preparatory dredging, an over-budget tender and redesign, while Gothenburg divides fairway and port-side responsibilities. Port Hedland and Ramayapatnam use more discrete capital-dredging packages, with Ramayapatnam's package arriving inside a greenfield port that had already been under construction for almost four years. Package history and structure are therefore primary analytical variables.
Ramayapatnam demonstrates the denominator problem. The 4 April 2025 government record placed the INR 4,929.39 crore whole port at 52.95% and the 13 February 2026 record still classified it under construction. DEME's basin, turning-circle, berth-pocket and reclamation package was awarded on 16 June 2026. The earlier percentage cannot measure a later contract, and the award cannot prove breakwater completion, cutter-suction mobilisation, dredged quantity, accepted reclamation, hydrographic clearance, navigation aids, VTMS, rail access, berth handover or first vessel service.
Cleveland's USD 11.7 million award sets approximately 250,000 cubic yards and two 2026 windows, but the first calendar window is not itself completion evidence. The delivery record must show plant mobilisation, measured upper-river production, the actual split among upland processing and confined disposal, post-dredge hydrography, and the October return. That campaign also sits inside a constrained sediment system: the Port awarded an SPMF bridge through 2029, USACE is assessing short-term placement alternatives, and CHEERS remains in design, permitting and funding rather than current operating capacity.
New Haven, Richmond, Tunisia, Mumbai, Cleveland, St. Joseph, and Georgetown show that containment, beneficial use, research placement, environmental review, and disposal pathways can shape programme sequence and stakeholder exposure as directly as dredging volume or design depth. New Haven separates fine material between two borrow pits and open water, sends sand to shellfish habitat and rock to a reef site, but its bid close does not prove that any route is ready or receiving material. Richmond's RFP links 14 reaches to suitable material placed at Montezuma Wetlands, but DMMO suitability and a tender route do not prove accepted receipts. Georgetown shows how an 18-year maintenance gap can convert recurring operations into navigation recovery: the selected action limits the current method to cutterhead dredging and existing upland placement areas, excludes ocean disposal, and keeps the 390,000-cubic-yard base plus 170,000-cubic-yard option separate from future maintenance quantities. Tunisia shows in parallel why a procurement portal marked complete cannot prove containment, dredging, placement, or acceptance. Mumbai adds a different control stack: DS1 is designated but non-exclusive, vessel movements require VTS coordination, the general SOP expects digital tracking and 15-day reporting, and project-specific permission still has to be evidenced.
Bujumbura shows why portfolio status, field targets, package handover, and resilience planning cannot be collapsed into one date or percentage. The active AfDB/EU package still requires dated post-March-2025 evidence for the protective dike, dredging, quays, marine dock, roads, and equipment. The October 2024 JICA ceremony closes only its separate grant package. The March 2026 UNDP study establishes a resilience investment track rather than built assets. The end-2026 infrastructure target and MapAfrica's 31 December 2027 programme date remain different schedule boundaries.
Madagascar now has a signed IDA agreement and a first package map, but not one marine contract. The final appraisal allocates US$30 million to Majunga, US$32 million to Tulear and US$29.94 million to Pangalanes within a US$102.24 million component. The 26 May plan records Majunga works as pending, canal maintenance and dredging equipment as under review, a canal landing-stage package as cancelled, and canal supervision as pending; it does not list active main Tulear or canal-dredging works packages. Port rehabilitation contains no port dredging, while canal dredging remains subject to site-specific safeguards and a Dredging Management Plan.
Port Mansfield and Ruwais LNG both have named plant or field-operation evidence without a published acceptance file. Port Mansfield's dredges and pipeline routes do not supply measured quantity, accepted depth, post-dredge survey, material receipt or final completion. Ruwais LNG's 15 million cubic metre award and 24-hour marine notice establish channel execution and disposal controls, but not final hydrography, quantity reconciliation, disposal close-out, permanent navigation aids, jetty handover or marine operating approval.
Cotonou publishes 69% physical progress and 72% overall progress on a Terminal 5 page that still lists 2021-2024. Concrete Layer Innovations separately identifies CHEC's 350-metre breakwater extension, 891-metre revetment and about 22,000 cubic metres of ACCROPODE II units. Together the sources establish active construction, not a current programme or a dredging percentage. Basin and access-channel quantities, material routing, accepted hydrography, reclamation handover, berth readiness and opening remain unpublished.
Twenty-four Confirmed public records form the denominator for this edition. Open each record to inspect its phase, scope, current status, image, and complete project source trail.
Deep-water ports, dredging and reclamation / Tender
The approximately 200-hectare nearshore reclamation and shore-protection EPC package is awarded; as of 15 July 2026, the owner tender page lists the offshore dredging, reclamation and protection-bund HAM package closing on 17 July and the Daman marine-sand investigation closing on 15 July, while no award or AOC is published for either package or for the 10.14-kilometre offshore breakwater
11 structured project sourcesPort infrastructure / Award
Dredging contract signed; enabling and supervision sequence forming
7 structured project sourcesPort infrastructure / Mobilisation
Concession signed; operating transfer complete and August maintenance mobilisation remains to be evidenced
9 structured project sourcesPort infrastructure / Construction
Outer harbor dredging and ERDC placement monitoring active
6 structured project sourcesPort infrastructure / Award
Dredging contract signed for 2027 start
9 structured project sourcesPort infrastructure / Award
A$50 million dredging contract awarded; federal sea-dumping application remains an open evidence gate before September mobilisation
10 structured project sourcesMarine infrastructure / Approval
IDA financing signed; marine packages are planned, under review, pending, cancelled, or absent from the reviewed plan
10 structured project sourcesPort infrastructure / Award
USD 11.7 million award confirmed; no 2026 field execution is documented
10 structured project sourcesPort infrastructure / Construction
Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery
10 structured project sourcesPort infrastructure / Construction
Main quay works under construction after the Q4 2024 start
8 structured project sourcesPort infrastructure / Award
USD 3.587 million award; July 2026 start expected but mobilisation remains unconfirmed
7 structured project sourcesPort infrastructure / Award
Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed
12 structured project sourcesMarine infrastructure / Construction
Ongoing at programme level; March 2025 remains the latest quantitative Phase I physical-progress baseline
8 structured project sourcesDredging / Tender
Tender E.47/2026 remains open; bids due 23 July 2026 after one corrigendum
8 structured project sourcesDredging / Mobilisation
Concession signed; 1 August operating transition remains scheduled, with the 13.3-metre baseline still controlling
8 structured project sourcesDredging / Tender
Initial state dredging phase completed and a separate private berth stage is active; the federal 40 ha north-platform construction-dredging tender was declared void on 8 July 2026, with no rebid confirmed
8 structured project sourcesDredging / Completed
The Government of India reports Phase VI complete and Kamarajar operating at 18.0 metres draft; the post-dredge survey sheet and a first fully laden Capesize call are not published
6 structured project sourcesPort infrastructure / Approval
Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed
5 structured project sourcesPort infrastructure / Tender
Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded
5 structured project sourcesDredging and waterways / Tender
IFB amendment 0007 posted 16 July 2026; bids closed 17 July; no award or notice to proceed posted
5 structured project sourcesDredging and waterways / Construction
Callan Marine dredging has reached the Gulf Intracoastal Waterway junction; the Navigation District says the next work front is the harbor and turning basin
7 structured project sourcesDredging / Evaluation
Three preliminary bids opened for MFP-364.003; evaluation and award remain pending
5 structured project sourcesDeep-water ports and energy terminals / Construction
Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published
7 structured project sourcesPort infrastructure / Construction
The port authority reports 69% physical progress and 72% overall progress, while its published 2021-2024 delivery period is no longer current
6 structured project sourcesMethod
Twenty-four public records met four tests at the 20 July 2026 cutoff: a named asset or programme, a defined marine scope, Confirmed evidence from an accountable party and a structured project page. Each project is counted once at its latest evidenced phase. New York and New Jersey marine terminals are at evaluation because three preliminary totals are public but award and the first work order are not. New Haven, Richmond, Mumbai and Vadhvan remain at tender; Progreso is a tender-stage reset after the federal package was declared void. Port Douglas remains at approval because the scope and delivery window are defined without a contractor or mobilisation record. Six projects are at award. Paranaguá is at mobilisation because its concession is signed but operating transfer and accepted deepening remain open. Valencia, Bujumbura, Gothenburg, St. Joseph, Port Mansfield, Ruwais LNG and Cotonou Terminal 5 have current field or construction evidence. Kamarajar Phase VI is complete on the government record, with close-out evidence still to follow. The denominator is this fixed 24-project set, not the global dredging market.
Owner-listed opening and current closing dates for the offshore HAM and Daman marine-sand investigation procurements.
Owner-side package values and reviewed award or evaluation state for the nearshore, breakwater, and offshore HAM packages.
Official procurement-stage boundary for Vadhvan's offshore dredging, reclamation and protection-bund HAM package.
Award, three-port scope, sequence, plant, and differentiated dredged-material routes.
Official second-call, single-lot, budget-funded maritime-works procurement record; its Complet status is bounded from physical completion.
National-agency evidence that the approximately TND 125 million three-port contract had been signed, without proof of physical mobilisation.
Owner notice establishing the separate supervision and technical-assistance procurement for all three port complexes.
Early environmental-management participation record, bounded from later project-specific campaign approvals and physical delivery.
Official tender and document route for the toll-backed VNT concession.
Pre-award recommendation after the three-stage evaluation, kept separate from formal award and signature.
Official award basis for the VNT concession record.
Contract signature, concession-company formation, asset and worker transfer, toll change and controlling authority boundary.
Current fieldwork and sediment-placement research basis for St. Joseph Harbor.
Signed remaining-works contract, planned start, value, fairway length, and completion frame for Malmporten.
Preparatory-work completion, over-budget tender stop, quay-procurement stop, fairway optimization, retender and planned 2027 start.
Historical whole-program quantity, material, parallel-works and seasonality assumptions, kept separate from the current remaining-works contract.
Port-owner award and channel-resilience scope for Port Hedland.
Controlled design depth, dredging envelope, disturbance footprint, plant options, SG7C placement and monitoring basis for the Port Hedland resilience package.
Federal application SD2026-4091 and the open permit boundary for loading and dumping up to 800,000 cubic metres.
Final US$102.24 million port-and-waterway component, eight-subcomponent structure, component allocations and 200-kilometre Pangalanes scope.
No-port-dredging boundary for Majunga and Tulear, canal turbidity and dredged-material risks, and site-specific safeguards required before related procurement or works.
Public approval announcement and programme-level description of the two ports and 200-kilometre canal corridor.
Package values, planned procurement dates and pending, under-review or cancelled states; planned dates are bounded from issued notices and awards.
Signed US$200 million IDA framework, total US$305 million project structure, co-financing condition and 30 September 2031 closing date.
Proposed US$100 million AIIB co-financing and Category A environmental framing, kept separate from approval or effectiveness.
Latest reviewed quantitative Phase I field baseline: 45% on the 545-metre protective dike, follow-on quay and marine-dock scope, 11.7 kilometres of access roads, funding split, and end-2026 infrastructure target.
Current ongoing status, five-component programme boundary, UA35.732 million commitment, approval and signature dates, and 31 December 2027 planned completion date.
2024 high-water damage context and the March 2026 engineering-study boundary for phased reinforcement, drainage, and resilient expansion planning.
9 April award, contractor, value, planned quantity, two windows, intended material routes, and the boundary between those plans and unreported 2026 execution.
Short-term placement alternatives, annual upper-river sediment baseline and capacity constraints; the scoping document is bounded from route selection or authorization.
Authorized channel geometry, approximately 225,000-cubic-yard annual dredging requirement, DMMP status and navigation-economy baseline.
Separate prior-year DMYLES contract, lower-river scope, planned quantity and CDF route, retained as history rather than 2026 evidence.
USD 4 million SPMF extension award and through-2029 bridge; award is bounded from completed construction and operating capacity.
Observed split between SPMF processing and silt-basin storage, with the separate Cleveland-Cliffs dock quantity excluded from the federal-channel total.
DMMP and EIS review framework, retained as planning evidence rather than a final selected solution.
SPMF operating and berm-raising plan, annual placement assumptions and capacity intervention; planned work is bounded from completion.
Port-side description of the Cuyahoga shipping channel, CDF management, sediment harvesting and beneficial-use system.
Long-term 3.85-million-cubic-yard beneficial-use concept, design, permitting and funding status; not current placement capacity.
Port-side contract and interface basis for Skandia Gateway.
USD 3.587 million award, current base and option quantities, July start expectation, less-than-three-month window, target depth, and stakeholder-safety briefing for Georgetown Harbor.
Annual dredging through 2008, subsequent shoaling history, industrial-navigation context, selected cutterhead method, upland placement areas, no-ocean-disposal route, and broader future operations-and-maintenance envelope.
Approximately 560,000-cubic-yard selected-action boundary, existing upland placement, mainstem Sampit exclusion, draft public review, and 10 November 2025 Section 401 certification.
Award, scope, plant, and delivery-window basis for Ramayapatnam.
Clearance boundary and conditions for the wider Phase I port before construction initiation.
Government event record establishing initiation of the wider port programme, distinct from the later dredging package.
Breakwater lengths, armour-unit quantities, casting start and placement start for the wider port works.
Government research record for the additional breakwater wave-flume studies and hydraulic-stability boundary.
Proposed north-breakwater, navigation-aid and VTMS funding items, explicitly bounded from approvals, awards and completion.
Official record that RPDCL was developing the approximately 5.5-kilometre Tettu connection under Gati-Shakti policy and that work on the serving-station yard was at an advanced stage.
INR 4,929.39 crore whole-port cost, 52.95% physical-progress baseline, under-implementation status and 34.04 MMTPA Phase I capacity.
Current government classification of Ramayapatnam as under construction before the DEME award.
Current contractor-side two-phase capacity, draft and cargo-system context, bounded from delivery acceptance.
Owner-listed scope, publication date, corrigendum count, current bid deadline, and CPPP tender identifier for E.47/2026.
Three annual cycles, contract estimate, bid security, plant thresholds, payment models, DS1 route, monitoring, and acceptance requirements.
Priced-work boundary confirming dredging, transport, dumping, mobilisation, and demobilisation within the tender package.
Current procurement-stage boundary; reviewed without evidence of completed technical evaluation, financial opening, or award.
Annual maintenance-dredging accounting line for actual 2024-25, revised 2025-26, and budget 2026-27; not contract value or physical quantity.
General one-month permission, vessel, VTS, AIS, logbook, reporting, and authorized-dumping controls; not project-specific permission.
Preceding E.47/2023 contractor, value, scheduled dates, and work-in-progress status as at October 2024; historical context only.
Earlier multi-cycle maintenance awards and recurring package structure; historic values and contractors are not carried into 2026.
Auction winner, 20 live bids, tariff discount, grant fee, first-five-year investment, and target-draft basis for the Paranaguá concession.
Homologation boundary confirming the selected consortium while leaving signature, transfer, mobilisation, and delivery for later evidence.
Term, CAPEX, contract value, concession boundary, phase programme, dredging, survey, rock-removal, berth, VTS, navigation-aid, and Antonina transition basis.
Federal contract-signature and investment evidence, bounded from later operating transfer or accepted deepening.
Contractor-side 12 March signature date, 25-year term, PPCC operating vehicle, and mobilisation boundary.
Expected 1 August 2026 operating and tariff transfer; the notice is not evidence that transfer or tariff collection occurred.
Separate pre-handover Vox Amalia campaign and end-June target, kept apart from concession fleet, completion, and performance.
Current 13.3-metre operating draft, 15.5-metre target, March 2026 bathymetry, VTS status, PDO charge, concession area, and reporting baseline.
Current lender definition of the main quay, ancillary quays, 137-hectare reclamation, basin deepening, dismantling interfaces, Q4 2024 physical start, and contractor consortium.
Pre-tender design, estimated budget, 58-month planning period, caisson and consolidation prescriptions, dredged-material characterization, and operability requirements; explicitly non-final at publication.
Tender-close evidence and terminal design context, bounded from contractor selection or physical works.
Owner award to the ACCIONA-Jan De Nul-Grupo Bertolin joint venture, separate from the later concession and physical start.
EUR 489 million contractor-side award, primary and auxiliary quays, 126-hectare paved-terminal definition, and planned reuse of dredged material from Valencia and Sagunto.
Separate 50-year construction-and-operation concession and EUR 1.098237 billion private-investment proposal, bounded from civil acceptance and operating readiness.
Contractor scope, about 25 million cubic metres of dredged material, and reuse intent where feasible; quantity and reuse plan are not accepted output.
Signed owner record for the December 2023 procedure, EUR 489.18 million excluding VAT award, Q4 2024 physical start, and execution boundary.
Void-status and federal package-scope boundary for the 40 ha north platform; no bidder, award, mobilisation or rebid is inferred.
Macro geometry, 12.9 million m3 baseline, two-platform programme and initial state-phase completion entry; not a replacement federal contract.
Official weekly change record moving the north-platform package from proposal review to void.
Original national tender route and calendar; its 24 June proposal-opening date is preserved separately from Proyectos Mexico's 26 June date.
Boundary between the completed state phase and separate SSA Marine Mexico berth stage; neither proves execution of the void federal platform package.
Earlier state-phase rock quantity, depth, width and length progress, with exact Progreso cutter-head imagery.
Project-specific vessel arrival and exact port-context imagery for the initial state phase.
Technical context for the photographed vessel only; it does not establish contractual responsibility for the void package.
Government completion status, channel-depth changes, 18.0-metre operating draft and stated 170,000 DWT capability.
Owner record for Van Oord, the 24 October 2024 award, INR 4.407 billion contract value and June 2026 expected completion.
Foundation-event record describing the Phase VI capital-dredging investment as INR 5.45 billion; not a final account.
Tender-stage record for the INR 3.8 billion value, 540-day period and initial bid-opening date.
Owner planning record for the 13.23 million cubic metre draft-feasibility basis and INR 5.492 billion estimate.
Current owner-side hydrographic, declared-depth and maintenance responsibility; not the unpublished Phase VI acceptance survey.
Controlling 2026 owner record for quantity, cutter-suction method, temporary pipeline, Killaloe route, water-quality monitoring and delivery window.
Historical evidence that clean sand from an earlier campaign was removed from Killaloe before the next dredging; not a 2026 material-reuse commitment.
Exact-location historical contractor and image context, kept separate from the unidentified 2026 delivery party and scope.
Current deadline, cost range, evaluation route, depth, 14-reach scope and Montezuma destination.
Earlier procurement notice retained for change history; its anticipated dates do not control the updated RFP.
Historical 350,000-cubic-yard planning quantity, lower cost range and target dates, kept separate from current solicitation terms.
Monitoring route for condition and post-dredge survey evidence; not a current accepted quantity or result.
Authorized and funding-limited depth context, kept separate from the current -37-foot contract requirement.
Controlling procurement record for amendment history and the 17 July bid close; no public award, notice to proceed or mobilisation is carried from the closed solicitation.
Owner and sponsor record for the 40-foot channel programme, nearly 4.5 million-cubic-yard scale and planned fall 2026 to spring 2028 construction window.
Planning quantities and the five material destinations; estimates remain subject to post-maintenance surveys and do not prove awarded quantities or accepted receipts.
Federal navigation-project geometry and operating context for the entrance channel, inner harbor and turning basin.
Authorized design and environmental baseline for channel widening, deepening, material classification and placement; retained as programme basis rather than current production evidence.
Owner-side field update for the GIWW-junction milestone, next harbor and turning-basin sequence, contract value, funding, delivery deadline and safety characterization.
Mariner notice for General Bradley and General Marshall, Daybeacon 18, floating and submerged pipeline routes, passing coordination and the notice window; the window is not treated as a contract extension.
Earlier permit-stage beneficial-use proposal and environmental review context, kept separate from current measured production and acceptance.
Design-stage drawing context for the approximate two-million-cubic-yard proposal, 206-acre beach-fill area and 10,770-foot placement range; not a current output record.
State programme context for surveys, design and agency coordination supporting beneficial-use placement planning.
Executed planning and coordination work order for surveys, design, USACE coordination and National Park Service review; not a construction acceptance record.
Federal place record for channel setting and a 14-by-125-foot geometry description, retained alongside the owner's 15-by-125-foot target pending a controlling survey and datum.
Official work-order scope across Port Newark, Elizabeth-Port Authority Marine Terminal, Port Jersey-Port Authority Marine Terminal and Howland Hook, with the advertised USD 50 million to USD 60 million estimate range.
Official preliminary table listing Donjon Marine at USD 51.424 million, Jay Cashman at USD 54.4312 million and Posillico Civil at USD 68.498 million without establishing award.
Official addendum incorporating terminal-specific sediment reports and supporting data into the procurement record.
Final clarification assigning upland-facility selection to the contractor and retaining receiving-state acceptance as a material-routing condition.
Owner route for current construction advertisements and preliminary bid-result records used to monitor evaluated result and award.
Official marine award defining approximately 15 million cubic metres over a 5-kilometre, 245-metre-wide access channel plus navigation aids.
Official operational notice defining phased 24-hour dredging, the access-channel work area, two offshore disposal sites, environmental buoys and a silt curtain.
Latest owner status confirming the project remains under development for 2028 commercial operations and has 90% of planned capacity committed.
Owner page for the 20-hectare bulk terminal, CFAF 98.3 billion excluding-tax project cost and undated 69% physical and 72% overall progress figures; its 2021-2024 period is not treated as a current completion date.
Project-specific evidence for CHEC's 350-metre breakwater extension, 891-metre revetment, underwater placement and about 22,000 cubic metres of armour units.
Owner report defining Terminal 5 and improved nautical access separately from the north-quay and basin-expansion project; the latter's quay and dredging quantities are not assigned to Terminal 5.
Definitive award to Inros Lackner for continuing owner representation; it supports active oversight without establishing completion or accepted marine quantities.
Financing evidence for Terminal 5 and the separate Zongo access project, including basin dredging, channel widening and sea-wall work; EUR 80 million is not presented as the CHEC contract value.
Current financier record showing Ongoing status and a planned completion date of 12 February 2028; it does not replace the owner's missing revised construction programme.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
This report is a dated research snapshot, not an investment forecast, procurement recommendation, legal opinion, or delivery commitment. Review the linked project records and current briefings before acting on any individual project signal.