Ports & Dredging

Paradip's ninth extension keeps the 685-acre tender open

Published 21 July 2026 Updated 16 August 2026 Publisher IMWO Region Asia Pacific Confidence Confirmed
Bulk carrier alongside cargo yards and marine cranes at Paradip Port

Paradip Port Authority; local industrial-waterfront context, not the IDCO reclamation site

DCI has not closed its industrial-estate reclamation tender at Paradip. The current government page lists Corrigendum-9 and schedules bid submission and opening for 18 August. A public BOQ mirror puts 685 acres, a full peripheral bund, pumping and return-water pipelines, booster pumps, and both TSHD and CSD mobilisation inside the procurement.

Corrigendum-9 restarts the bid clock

CPPP publishes the procurement status: global item-rate tender, two covers, INR 1 crore EMD and Corrigendum-9's current 18 August submission and opening dates. An earlier stage snapshot does not establish completed opening or evaluation. CPPP does not publish bidders, prices, a work period or an award. Tenderkart is a public mirror of the BOQ work items, including 685 acres, bunds, pipelines, booster pumps, TSHD and CSD arrival, borrow-area dredging, compaction and backwash-water return. The photograph shows Paradip Port operations, not this project's current site or progress.

The BOQ joins dredgers, bunds and return water

This is not a dredger-only package. The mirrored work items sequence bund completion before the main reclamation run, then connect borrow-area dredging to pumps, pipelines, internal bunds, compaction and backwash-water return to sea. A weak interface at any one of those points can idle an expensive dredger spread or leave fill unaccepted.

Evidence conclusion

The award line is still blank

The procurement remains open. CPPP's current tender page moves submission to 15:00 and opening to 15:30 India time on 18 August. An earlier stage page showed technical opening after the superseded 21 July deadline, but that display is not evidence of a completed opening or evaluation after Corrigendum-9. CPPP has not published bidders, technical qualification, financial opening, contract value or award. The BOQ mirror is detailed enough to show the delivery chain, while final quantities and package boundaries still depend on the awarded contract.

Outstanding evidence

  • Named technical bidders and qualification outcome
  • Financial opening, evaluated price, award value and contractor
  • Final quantities, work period and notice to proceed
  • Borrow-area and pre-dredge survey confirmation
  • Peripheral-bund completion and internal-bund sequence
  • TSHD, CSD, pipeline and booster-pump mobilisation
  • Backwash-water route, environmental controls and water-quality records
  • Fill levels, compaction tests and final acceptance