How desalination contracts divide the marine works

Published 18 July 2026 Publisher IMWO Section Analysis
Aerial view of the Alkimos Seawater Desalination Plant under construction beside the Indian Ocean in June 2026

Water Corporation, Western Australia

Hawar tenders its intake and outfall separately. Algarve keeps both inside a design-build-operate contract, while Alkimos carries tunnels and offshore structures through an alliance. Rosarito's current invitation leaves the marine allocation undisclosed.

In this article

The package boundary matters before the pipe diameter

A desalination announcement can identify the plant capacity, developer and contract value while saying almost nothing about who designs, builds and accepts the seawater intake and brine outfall. That omission changes the opportunity. A marine contractor may face a stand-alone EPC tender, a subcontract inside a full-plant EPC, an alliance workstream or no disclosed package at all.

Six current projects use six different arrangements. The physical works are familiar across them: survey, tunnelling or trenching, offshore structures, large-diameter pipe, risers, diffusers, environmental controls and hydraulic testing. The contract that owns those interfaces is not familiar, and it cannot be inferred from plant capacity or coastal location.

Bid boundary check

Contract questions that define the marine package

Before pricing an intake or outfall, bidders need the contracting route, scope boundary, permits, live interfaces, commercial milestones and acceptance basis.

  1. 01

    Contracting vehicle and buyer

    The contracting vehicle may be a separate marine EPC, full-plant EPC, alliance, DBO, PPP or IWP concession, each with a different accountable buyer.

    Contracting route and accountable buyer are stated without inference.
  2. 02

    Physical marine boundary

    List intake structures, tunnels or trenches, pipelines, risers, outfall, diffuser, coastal shafts and owner-supplied connections inside the package.

    Included works, exclusions and tie-in points form one package map.
  3. 03

    Design and permit responsibility

    Responsibility for surveys, reference design, detailed design, environmental approvals, marine licences, temporary works and construction-method acceptance is allocated to named parties.

    Design authority and permit risk sit with named contract parties.
  4. 04

    Live project interfaces

    Connect marine plant, tunnel breakthroughs, onshore pumping, treatment process, power, storage and transfer systems to the same delivery sequence.

    Interface register identifies the work that can delay integrated commissioning.
  5. 05

    Commercial commitments and open allocations

    Commercial allocation spans bid evaluation, advance, securities, insurance, milestone payment, provisional acceptance, operating payments and long-term performance obligations.

    Payment and security terms match the actual marine risk period.
  6. 06

    Final marine system acceptance

    Final acceptance combines as-built survey, structural and pipeline tests, hydraulic performance, plume monitoring, treatment integration and accountable operating release.

    Acceptance evidence closes both the sea connection and plant interface.

Six live contracts

Where the marine risk sits

The same intake and outfall work reaches the market through very different contracting routes.

Bahrain Confirmed

Hawar SWRO offshore intake and outfall tender

Contract position
Separate marine EPC; two bids opened
Marine boundary
The intake and outfall are procured apart from the treatment plant and storage package, but no award is published.
Outstanding contract record
Official award, signed scope, offshore geometry, interface matrix, contract value and notice to proceed.
Portugal Confirmed

Algarve seawater desalination intake and outfall system

Contract position
Marine works bundled in design-build-operate
Marine boundary
Twin offshore intakes, pipelines and the brine outfall sit inside the awarded integrated contract.
Outstanding contract record
Offshore mobilisation, route-by-route installed quantities, environmental records, pressure testing and hydraulic acceptance.
Australia Confirmed

Alkimos Seawater Desalination Plant marine tunnels and offshore structures

Contract position
Alliance delivery with ten-year O&M
Marine boundary
Tunnels, offshore risers, intake structures and the diffuser share one alliance acceptance path.
Outstanding contract record
Outfall completion, permanent tunnel-to-riser connections, integrated testing, operating release and first sustained water.
Morocco Confirmed

Casablanca-Settat desalination marine works and common systems

Contract position
PPP with common marine systems in stage one
Marine boundary
The first stage carries marine and tunnelling systems sized for the full two-stage plant.
Outstanding contract record
Accepted common marine system, energisation, integrated hydraulic testing, provisional acceptance and first-stage operation.
Saudi Arabia Confirmed

Ras Mohaisen Independent Water Project and Marine Intake/Outfall

Contract position
IWP with full-plant EPC
Marine boundary
Intake, outfall and about 3 km of offshore work sit inside the main EPC rather than a public marine tender.
Outstanding contract record
Approved marine drawings, dated mobilisation, pipe-laying records, accepted as-builts, diffuser tests and hydraulic performance.
Mexico Confirmed

Rosarito 2,200 l/s desalination procurement

Contract position
Live invitation; marine allocation undisclosed
Marine boundary
The wider project includes intake and discharge works, but the invitation summary names only the plant and pumping plant.
Outstanding contract record
Ruling, signed package boundary, selected contractor, contract value and allocation of every CFE tie-in.

Hawar put the offshore works in their own tender

Bahrain's Electricity and Water Authority split the New Hawar SWRO scheme into three EPC packages: the 1 MIGD treatment plant, a separate offshore seawater intake and outfall, and two storage tanks with forwarding pumps. The marine facilities must accommodate an ultimate 3 MIGD plant even though the first treatment package is smaller.

Two marine bids were opened in December 2025. Ten plant bids and four storage bids were opened under their own tenders. A marine award has not been published. The immediate commercial question is therefore not the total plant value but the evaluation of the marine bids and the interface matrix that will connect three contractors through commissioning.

Algarve and Casablanca keep the marine system inside the main delivery vehicle

Algarve uses a mixed design, construction and operation contract. The EUR 107.923 million total includes EUR 102.785 million for design and construction through provisional acceptance and EUR 5.138 million for three years of operation. Two intake towers about 2 km offshore, separate large-diameter intake lines and a 2.13 km brine outfall sit inside that awarded contract rather than in a public marine tender of their own.

Casablanca-Settat uses a PPP with long-term operation and maintenance. Its first 200 million m3/year stage carries the common marine, tunnelling and electrical systems needed for the eventual 300 million m3/year plant. The first-stage contractor therefore owns capacity and acceptance interfaces that extend beyond the first-stage process train. In both projects, specialist marine work may still be subcontracted, but the public owner is buying an integrated system from the main delivery vehicle.

Alkimos puts tunnels, offshore structures and operation inside an alliance

Water Corporation, ACCIONA and Jacobs are delivering Alkimos through an alliance that also includes ten years of operation and maintenance. Stage 1 combines 50 GL/year of treatment capacity with a 2.5 km intake tunnel, a 4 km outfall tunnel, two offshore intake structures, four vertical risers and a 130 m diffuser with 20 ports.

The contract boundary does not remove interface risk; it changes where that risk is managed. Tunnel boring machines drive from shore to offshore risers while jack-up and support barges install piled structures and the diffuser. Survey control, breakthrough tolerances, lifting, grouting, exclusion zones and hydraulic acceptance must meet inside the alliance. Water Corporation's July 2026 update records the intake tunnel and offshore piling complete, with the outfall tunnel and diffuser connection still active.

Ras Mohaisen keeps the sea works inside the IWP EPC

Ras Mohaisen is financed as a 25-year independent water project. The L&T-Lantania EPC scope covers the full 300,000 m3/day plant, intake and outfall facilities, pumping, storage, grid works and solar PV. Lantania identifies 3 km of offshore work, while the environmental assessment identifies seabed trenching, dredging, pipe laying and marine monitoring.

The project is funded and under construction, but a separate marine award, accepted offshore geometry and installed pipeline length are not published. Suppliers need the EPC contractor's package map, not the water-purchase agreement headline, to see where marine design, vessels, pipe, monitoring and testing will be bought.

Rosarito still has an unresolved package boundary

Rosarito sits at the opposite end of the evidence spectrum. The live Compras MX invitation names construction of the desalination plant and pumping plant. A separate federal-state agreement lists intake works, brine discharge, conveyance, storage, electrical works and intake and discharge connections in the wider 2,200 l/s project. The public invitation detail does not say whether all of those components are inside one contract.

The proposal opening is now 24 July 2026 and the ruling is listed for 29 July. Compras MX also publishes a 50:50 technical-economic evaluation, a 30% advance, a 10% performance guarantee and separate liability and environmental insurance requirements. Those terms define bid security and cash-flow conditions, but they do not resolve the marine bill of quantities, construction method or responsibility for the existing CFE cooling-water interfaces. The signed scope has to do that.

The bid decision depends on the interface record

These projects cannot be compared by plant capacity and headline contract value alone. Hawar exposes a direct marine competition. Algarve and Casablanca place the sea connection inside integrated delivery. Alkimos manages it through an alliance. Ras Mohaisen places it inside the IWP EPC. Rosarito confirms the physical interface, while the current public invitation leaves the contract boundary undisclosed.

The package is not priceable until the contracting entity, scope, owner-supplied elements, survey and design authority, permits, weather and access risk, temporary works, testing responsibility, performance security, payment milestones and accepting party are identified. Until those fields are visible, an intake length or plant capacity is a design fact, not a commercial package.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Sources used

Source collections

Cite this article

International Marine Work Organization (2026). How desalination contracts divide the marine works. https://imwo.org/articles/article-desalination-marine-package-boundaries-2026-07-18