Current focus
Tartous port modernisation mobilised
Regional intelligence
Large-scale coastal development, utilities, ports, industrial waterfronts, and private destination programmes.
Regional coverage: project signals, client movement, procurement themes, and contractor activity are maintained through IMWO publishing standards.
Tartous port modernisation mobilised
16 project records connected to this region.
18 current analyses and briefs coded to this region.
21 public profiles identify active work or decision roles in this region.
Project coverage
UAE / Marine utilities / EPC agreement signed on 7 May 2026; no notice to proceed or marine mobilisation is published
award / Evidence reviewedSaudi Arabia / Marine utilities / EPC performance test completed on 19 February 2026; SWPC commercial-operation confirmation remains unpublished
commissioning / Evidence reviewedUAE / Deep-water ports and energy terminals / Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published
construction / Evidence reviewedOman / Marine utilities / Under construction; Nama PWP targets commercial operation in Q1 2027
construction / Evidence reviewedUAE / Marine utilities / ACWA lists commercial operations from Q1 2024; the 200 MIGD plant is operating, while final as-built intake and outfall geometry is not publicly disclosed
completed / Evidence reviewedBahrain / Marine utilities / Two bids were opened for Hawar's separate offshore intake and outfall EPC package on 25 December 2025; EWA still lists the wider desalination scheme as a future project and no award is published
tender / Evidence reviewedSaudi Arabia / Marine utilities / Sharakat is qualifying developers across five planned seawater reverse-osmosis projects; no individual RFP, award or project-specific marine package is public
prequalification / Evidence reviewedJordan / Port infrastructure / DFBOT proposals due 17 August 2026
tender / Evidence reviewedUAE / Port infrastructure / AED 84 million Newcastlemax upgrade agreed; design, package awards and delivery remain open
award / Evidence reviewedSyria / Port infrastructure / Operations active; modernisation equipment mobilising
early works / Evidence reviewedUAE / Marine utilities / PPA and EPC signed; cooling-water review and existing-plant tie-ins exposed, marine route unconfirmed
award / Evidence reviewedSaudi Arabia / Marine utilities / Project agreements, the L&T-Lantania EPC award and December 2025 financial close are evidenced, and ACWA's 3 March 2026 year-end report classifies the full 300,000 m3/day capacity as under construction; offshore mobilisation, installed intake or outfall geometry, first water and accepted production are not dated
construction / Evidence reviewedJordan / Marine utilities / Final technical and legal agreement signed; financial close still pending as of 7 July 2026
financing / Evidence reviewedIraq / Port infrastructure / Core marine assets built; terminal, tunnel, and commercial-operating interfaces remain under verification
construction / Evidence reviewedQatar / Port infrastructure / Owner reports 98% construction; full-system handover pending
construction / Evidence reviewedUAE / Marine utilities / Block A commissioned; remaining Phase 1 capacity in delivery
commissioning / Evidence reviewedCurrent research
EtihadWE's development arm has signed the Fujairah I EPC with NMDC Infra and Lantania Aguas. The 60 MIGD scheme includes a submarine intake tower, two GRP intake pipelines and a GRP marine outfall at the Port of Fujairah.
Evidence updated
Nama PWP still targets Q1 2027 commercial operation for Oman's 300,000 m3/day Ghubrah III plant. The four-line marine system is well defined on paper, but current public updates do not say how much of the intake and outfall network has been installed or accepted.
Evidence updated
SEPCOIII says Rabigh 4 completed its EPC performance test on 19 February 2026 at the 600,000 m3/day design capacity. It reported power use of 2.712 kWh/m3, falling to 2.659 kWh/m3 after photovoltaic generation. The contractor notice is strong commissioning evidence, but it is not an SWPC commercial-operation certificate.
Evidence updated
NMDC Group's Ruwais LNG marine package covers about 15 million cubic metres of dredging along a 5-kilometre, 245-metre-wide access channel and new navigation aids. A February 2025 ADNOC port notice shows that phased dredging had entered 24-hour execution, with two offshore disposal sites, environmental buoys and a silt curtain. The disclosed trail ends before final hydrographic acceptance and marine handover.
Evidence updated
ACWA lists Taweelah RO in commercial operation from Q1 2024 at 200 MIGD. Its marine appendices preserve proposed intake and outfall layouts plus 27.8 m3/s intake and 17.3 m3/s discharge assumptions used during bid-stage modelling. They do not disclose the final as-built route.
Evidence updated
The same Abu Dhabi industrial coast contains a power project with only cooling-water review in public, an operating 200 MIGD RO plant with a bid-stage marine design trail, and an industrial berth moving from Capesize service toward Newcastlemax. Their buyers, scopes and acceptance histories differ.
Evidence updatedDelivery network
Ruwais LNG project developer and marine-works client / Access-channel dredging and navigation-aids procuring entity / Petroleum-port governance principal through the Petroleum Ports Authority
Evidence reviewed
Water infrastructure developer / Desalination EPC and commissioning lead / Operations and maintenance provider
Evidence reviewed
Independent water project developer / Infrastructure investor / Project company sponsor
Evidence reviewed
Marine contractor / Dredging contractor / Offshore energy contractor
Evidence reviewed
Marine contractor / Dredging contractor / Offshore installation contractor
Evidence reviewed
Sole water and electricity procurer / Long-term capacity planner / Power and water purchase agreement counterparty
Evidence reviewedSearch the complete public index for this geography, compare the tracker records, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.
Search Middle East Open project tracker Review methodology