Regional intelligence

Asia Pacific marine construction intelligence

Island infrastructure, terminal upgrades, India east-coast greenfield ports, urban waterfronts, contractor alliances, and industrial marine works.

Projects, client activity, procurement and contractor appointments across Asia Pacific.

Latest item update 77 public projects 87 region-coded publications 62 active organizations
On this page

Current focus

Tuas Phase 2 and Westport delivery active

Tracker coverage

77 project records connected to this region.

Publication coverage

87 current analyses and briefs coded to this region.

Organization coverage

62 public profiles identify active work or decision roles in this region.

Project coverage

All current Asia Pacific project records

77 records
Confirmed

Nga Bay riverbank embankments and lake flow control

Vietnam / Riverbank embankment and urban flood outfall works / June 2026 government account reports embankment work and drainage-package mobilisation; subsequent reach acceptance and programme updates remain to be checked

delivery / Last checked
Confirmed

Makassar New Port phases 1A, 1B and 1C

Indonesia / Container quay and terminal phased development / Phases 1B/1C physically complete in Q4 2023 and operating from February 2024; Phase 1D described separately as demand-led development

completed / Last checked
Confirmed

Lach Huyen berth 4 and ancillary barge/service wharves

Vietnam / Container berth and ancillary barge/tug wharves / Berth 4 and ancillary wharves opened in April 2025; an August 2025 owner account reports conditional approval in principle for larger partially laden ships; HTIT records an October 2026 service launch

delivery / Last checked
Confirmed

Vietnam Southern Waterway Corridors: A1 Canals and A2 Rivers

Vietnam / Inland-waterway channel improvement and bank protection / A1 formal works invitation issued 28 September 2026; latest A1 amendments and the separate A2 participation position remain under review.

tender / Last checked
Confirmed

Lower Molonglo membrane-bioreactor renewal

Australia / Wastewater bioreactor foundations and commissioning / Excavation completed in June; August owner plan schedules foundation pours in October, November and December 2026

construction / Last checked
Confirmed

Weipa 2026 maintenance dredging campaign

Australia / Dredging / NQBP reported campaign completion on 1 September 2026: 63 days and about 1.16 million m³ removed

completed / Last checked
Confirmed

Vadhvan Greenfield Deep-draft Port

India / Deep-water ports, dredging and reclamation / Afcons disclosed receipt of VPPL's Letter of Award on 9 June 2026 for the 10.14 km offshore breakwater, valued at INR 53.01 billion excluding GST. The nearshore EPC award is separate; the offshore HAM procurement outcome and current field progress require their own records.

award / Last checked
Confirmed

Aktau Port Berths 3 and 12 Modernisation

Kazakhstan / Port infrastructure / ECEPP marks the berth first-stage and supervision invitations closed; the supervision page lists 10 September 2026 as its final deadline; later-stage and other-package participation remain unverified

tender / Last checked
Confirmed

Paradip 18.5m capital dredging and terminal-readiness interface

India / Capital dredging and navigation-channel deepening / Owner reports channel completion and inaugurated 18.5m capability; earlier berth-specific admissible drafts require their own operating amendment

completed / Last checked
Confirmed

Jurien Bay Boat Harbour entrance reconfiguration

Australia / Ports and coastal protection / April maintenance dredging complete; 170m northern breakwater extension in detailed design, with construction tender to follow

design / Last checked
Confirmed

Mus seawall at Car Nicobar

India / Coastal infrastructure / Recall tender is in post-bid evaluation; no public AOC or named EPC contractor

tender / Last checked
Confirmed

Dundee Beach boat-ramp maintenance

Australia / Public boat-launch infrastructure, maintenance dredging and fixed access / Northern Territory Tenders Online records T25-1462 as a 12-month awarded period contract to Polaris Marine Constructions at AUD 676,047.56 on an estimated-unit-rate basis

award / Last checked
Confirmed

Libertad Outfall dredging works

Philippines / Dredging / Group completion reported; Libertad closeout remains unpublished.

construction / Last checked
Confirmed

Parks Victoria Bays Maintenance Dredging Program

Australia / Maintenance dredging, approach-channel access and beach placement / Buying for Victoria records Birdon Pty Ltd on a current AUD 31.9 million contract starting 1 November 2021; Birdon describes a 2021-2030 term and names dredge Ballina with support craft Willie Tell and Bella, while site-level quantities and owner acceptance remain campaign-specific

delivery / Last checked
Confirmed

Tuas Port Phase 2 reclamation and terminal development

Singapore / Port infrastructure / Phase 2 reclamation stood at 79.5% in December 2025 and its planned six-berth handover remains unverified; the wider Tuas Port passed 25 million TEU in August 2026, but that operating total began with Phase 1

delivery / Last checked
Confirmed

Snapper Creek State Boat Harbour shoreline protection works

Australia / Port revetment repair and armour-rock placement / Queensland Transport and Main Roads disclosed Contract MSQ25017 with Hunter Contractors Pty Ltd at AUD 1,981,207 on 10 July 2025, and Maritime Safety Queensland announced a 2 September 2025 construction start; no cited official source confirms installed quantities, completion, acceptance or final account

construction / Last checked
Confirmed

Geraldton Port Maximisation marine works

Australia / Port infrastructure / MGN Civil holds the surge-protection breakwater award; wider dredging, berth and tug-harbour packages remain separately unconfirmed

award / Last checked
Confirmed

Lower Yarra River Maintenance Dredging Program

Australia / Urban waterway maintenance dredging, navigation access and in-river material placement / Buying for Victoria records Australasian Marine Associates on a current AUD 1.93985 million contract starting 8 September 2021; Parks Victoria confirms AMA delivered Campaign C in 2024, while the owner programme was reported complete and the next funding cycle remained open

delivery / Last checked
Confirmed

NW-1 Bihar-West Bengal: six steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Cleghorn Mfg. Co. signed the six-location bundled supply and installation contract on 24 April 2025; public evidence does not confirm final sites, fabrication, installation, commissioning or acceptance

award / Last checked
Confirmed

NW-1 West Bengal: seven 30 m steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Nalanda Engineering Enterprise signed the seven-location bundled supply and installation contract on 3 April 2025; public evidence does not confirm fabrication, installation, commissioning or acceptance

award / Last checked
Confirmed

Tinian seaport P-940, P-1001 and P-1002 design

United States / Naval and civil seaport wharf, breakwater and harbor-dredging design / MDPAC JV holds a USD 12.616m architect-engineer task order through 31 December 2026 for P-940 wharf improvements, P-1001 breakwater restoration and P-1002 harbor dredging and Finger Pier A removal; 13 named design-chain subaward records total USD 4.055m, while no construction award or mobilisation is evidenced

design / Last checked
Confirmed

P-835 Lima Wharf and Inner Apra Harbor dredging

United States / Naval-wharf and inner-harbor dredging design / MDPAC JV holds the USD 3.335m P-835 design task order, expanded in August 2025 from DD1391 and 15% design into a design-bid-build package and extended in March 2026 to September 2028; no construction award or physical dredging is evidenced

design / Last checked
Confirmed

Hillarys Boat Harbour jetties A, F, G, H and J replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract

completed / Last checked
Confirmed

Fremantle Fishing Boat Harbour Jetty 3 replacement

Australia / Marinas, pontoons and berthing infrastructure / Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales

completed / Last checked
Confirmed

Apollo Bay Harbour seawall construction

Australia / Harbour seawall renewal and coastal asset protection / Buying for Victoria lists C26-0068 as a current AUD 896,000 construction contract with Maintenance Concepts Pty Ltd for 20 July to 21 September 2026; the portal exposes neither an award or signing date nor evidence of physical mobilisation

award / Last checked
Confirmed

Colombo West Container Terminal II Western Breakwater Extension Design

Sri Lanka / Deep-water port expansion, breakwaters and reclaimed logistics land / Dohwa-led detailed-design contract awarded in April 2025; SLPA's May 2026 planning document confirms the engineering study but leaves financing, construction procurement and field start open

design / Last checked
Confirmed

NW-1 Bihar: ten steel floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / Signed with Merolyn on 11 November 2025; procurement is under implementation, while physical delivery is unverified

award / Last checked
Confirmed

NW-1 West Bengal Lot A: five concrete floating jetties

India / Inland-waterway floating jetties, gangways and passenger facilities / IWAI signed the five-site Lot A contract with West Coast Marine Yacht Services on 18 March 2026; the procurement plan lists the package under implementation, but fabrication, installation and site acceptance remain publicly unconfirmed

award / Last checked
Confirmed

West Bengal 45-jetty contract ledger

India / Inland-waterway floating jetties, gangways and passenger facilities / World Bank data identifies 21 direct works contracts across the 29-jetty Phase I and 16-jetty Phase II programme; the June 2026 ISR says 44 of 45 locations are complete with Metiabruze under implementation, while its results table says all 45 are complete

construction / Last checked
Confirmed

Townsville MSQ Base wharf fender-pile replacement

Australia / Wharf maintenance, fender piles and marine asset renewal / Queensland TMR awarded MSQ26005 to Pacific Marine Group on 11 May 2026 for AUD 423,687; no public milestone establishes mobilisation, pile quantities, installation method, completion or acceptance

award / Last checked
Confirmed

Poona boat ramp and access-channel upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Australian Marine & Civil received CN-23611 on 29 July 2025; MSQ recorded dredging and foreshore nourishment from 9 to 27 February 2026 and a ramp closure from 16 February while upgrade works continued, but no later owner completion or acceptance notice was located by 6 August 2026

construction / Last checked
Confirmed

Newell Beach all-tide boat ramp upgrade

Australia / Public boat-launch infrastructure, capital dredging and fixed access / Queensland TMR completed the upgraded all-tide facility in May 2022 after Australian Marine & Civil delivered the main works under CN-17011; the published contract disclosure rose from AUD 2,560,154 to AUD 2,603,835 after a variation

completed / Last checked
Confirmed

Preah Sihanouk Marine Fisheries Inspectorate boat mooring and jetty

Cambodia / Marine infrastructure / Taing Cheng Oing Construction & Import Export signed package SCMFP FiA/CW-03 on 9 March 2026; ADB reports a financed amount of 472,336.05 without currency or full contract value, and mobilisation or physical start is not independently confirmed

award / Last checked
Confirmed

Warrawong Parklands Kully Bay seawall reconstruction

Australia / Foreshore seawall and rip-rap protection / Civil Constructions holds the AUD 3,814,475 Warrawong Parklands seawall contract and NSW Planning reports construction underway at Kully Bay; the 30 November 2026 contract end and owner year-end target remain programme dates rather than completion evidence

construction / Last checked
Confirmed

Hooghly four-location floating passenger-jetties package

India / Inland-waterway floating jetties, gangways and passenger facilities / Two lots were signed on 16 August 2024 for Tamlipara, Chinsurah, Metiabruze and Pujali; the June 2026 World Bank ISR says Metiabruze remains under implementation but its results table says all 45 project jetties are complete

construction / Last checked
Confirmed

New Woodman Point Ammo Jetty

Australia / Marine infrastructure / Advanteering Civil Engineers has completed detailed design and started early off-site construction under DOT413022; on-site work is planned from spring 2026 but no dated mobilisation evidence has been published

construction / Last checked
Confirmed

Woodman Point western boat ramp and Fremantle Jetty 1 renewals

Australia / Marinas, pontoons and berthing infrastructure / Jetty and Marine Constructions holds one design-and-construct contract covering the Woodman Point western boat ramp and Fremantle Fishing Boat Harbour Jetty 1; Woodman Point field works began under a 27 July 2026 closure, while a dated Fremantle mobilisation record has not been published

construction / Last checked
Confirmed

Me-Mel Goat Island Western Broadside Wharf repair

Australia / Port infrastructure / Western Broadside Wharf, adjacent seawall and access-pontoon repairs are underway under two NSW contracts through August and September 2026; the published notices name Polaris Marine Constructions and Clement Marine Constructions but do not disclose their exact package split

construction / Last checked
Confirmed

Yorkeys Knob boating facility

Australia / Recreational harbour, breakwaters, dredging and boat-launch infrastructure / The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works

completed / Last checked
Confirmed

Bangladesh WD17 Fish Landing Stations and Markets

Bangladesh / Port infrastructure / World Bank completion reporting confirms three fish landing stations and two fish markets completed by project close on 28 November 2025; five other sites in the original 10-site package could not start because of land-tenure disputes

completed / Last checked
Confirmed

Hunan Inland Waterway Green Port programme: Daorenji, Songyanghu III and Songmu II

China / Inland-waterway green-port programme, open-piled bulk and general-cargo berths / Daorenji's main marine structure was reported complete in July 2026 with equipment installation and commissioning next; Songyanghu III moved from 1,556 precast deck panels into field installation in January 2026; no current Phase II construction evidence has been found for Songmu. AIIB still lists the proposed sovereign financing as Proposed

construction / Last checked
Confirmed

Busan New Port West Container Terminal Phase 2-6

South Korea / Deep-water ports and automated container terminals / BPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening target

construction / Last checked
Confirmed

Port of Tanjung Pelepas Berth Zero

Malaysia / Deep-water ports and container terminals / Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028

construction / Last checked
Confirmed

Colombo West International Terminal

Sri Lanka / Deep-water ports and automated container terminals / Phase 1 has operated since April 2025 and handled one million TEU in its first year; the 1,400-metre quay was complete by March 2026 while Phase 2 crane deployment and full-terminal construction continue

construction / Last checked
Confirmed

Sagar-Eastern Channel capital dredging

India / Port infrastructure / SMPK completed a non-binding global market EOI for phased capital dredging; a formal RFQ, works award and dredging contractor are not verified

tender / Last checked
Confirmed

Kandla Cargo Berths No. 1-6 upgrade

India / Port infrastructure / DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified

design / Last checked
Confirmed

Kandla Multipurpose Cargo Berth No. 17

India / Port infrastructure / DPR work started in March 2025; no construction RFP, PPP award, concessionaire or works contractor is verified

design / Last checked
Confirmed

Chennai Port Berth 19A North Quay reconstruction

India / Port infrastructure / Technical audit and detailed engineering are commissioned through 31 December 2027; no construction tender, award or works contractor is verified

design / Last checked
Confirmed

New Zealand regional-port dredging barge

New Zealand / Dredging / NZD 8 million of government co-funding confirmed; designer, shipyard, build contract and first port assignment not disclosed

planning / Last checked
Confirmed

Can Gio International Transshipment Port

Vietnam / Deep-water ports and container terminals / Investor consortium approved on 11 April 2026; environmental approval, land and water handover, marine works award and physical mobilisation remain unannounced

approval / Last checked
Confirmed

Bangladesh Bay Terminal marine infrastructure

Bangladesh / Port infrastructure / IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started

design / Last checked
Confirmed

Port Douglas Boat Harbour 2026 maintenance dredging

Australia / Port infrastructure / Owner-defined cutter-suction campaign scheduled from July to October 2026; contractor and mobilisation remain unconfirmed

approval / Last checked
Confirmed

Patimban Port Phase 1-2 expansion

Indonesia / Port infrastructure / Phase 1-1 is completed and partly operating; Package 5 car-terminal and Package 6 container-terminal works remained active through June 2025; Package 7 construction lacks a current owner or contractor mobilisation date

construction / Last checked
Confirmed

Kamarajar Port Capital Dredging Phase VI

India / Dredging / The Government of India reports Phase VI complete and Kamarajar operating at 18.0 metres draft; the post-dredge survey sheet and a first fully laden Capesize call are not published

completed / Last checked
Confirmed

Gopalpur Industrial Park 100 MLD desalination PPP

India / Marine utilities / Four IFC advisory procurements define transaction preparation; the 100 MLD PPP, marine site, concession and works remain unawarded

planning / Last checked
Confirmed

Singapore DTSS2 Tuas WRP nearshore outfall

Singapore / Marine utilities / Nearshore outfall and Contract 1A permanent works were substantially completed on 14 August 2023; wider DTSS2 and Tuas WRP completion, commissioning and discharge acceptance remain open

construction / Last checked
Confirmed

Ramayapatnam Port capital deepening works

India / Port infrastructure / Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed

award / Last checked
Confirmed

Westport Kwinana container port and marine infrastructure

Australia / Port infrastructure / Marine reference design, investigations, environmental-review preparation, and construction planning active; Westport Bill remains before Parliament

design / Last checked
Confirmed

Port Hedland Zone 5 Bypass Channel

Australia / Port infrastructure / A$50 million dredging contract awarded; the federal sea-dumping application remains unresolved ahead of planned September mobilisation

award / Last checked

Current research

Latest region-coded publications

6 shown / 87 current
Historical Cho Lach canal view with boats, bank paths and a steel bridge; 2010 according to source metadata.
Brief / Confirmed

Cho Lach: Dredging and the A3 Bridge Construction Interface

Vietnam's A1 invitation combines improvements to Cho Lach, Rach Ky Hon and Rach La canals in a 24-month works contract. The signed 28 September 2026 notice specifies dredging, embankments, drainage and local roads, with rated technical and non-price factors weighted at 50% and the financial bid at 50% [1]. The 13 August procurement table places Cho Lach 2 Bridge and its access roads in a separate A3 package [2]. The canal programme therefore interfaces with the separately planned A3 bridge and access-road works.

Updated
Nga Bay diagram links Xeo Vong, Cai Con and Soc Trang bank reaches to 22 planned stormwater outlets and Xang Thoi Lake controls
Brief / Confirmed

Nga Bay: Hand Over Each Riverbank With Its Drainage Connections

Nga Bay's riverbank and drainage works were proceeding on different programmes in Can Tho's June 2026 progress account. Package 1 covered embankments and Pham Hung green infrastructure, with completion then expected by 31 December 2026. Package 2 covered storm drainage, sewer collection and wastewater treatment, with completion expected in November 2027. Across the scheme, about 3.1 km of new banks along Xeo Vong, Cai Con and Soc Trang connect to a planned stormwater system with 22 outlets and to works at Xang Thoi Lake. That combination makes the drainage connection a specific handover question for each completed bank reach. [1][2]

Updated
Makassar New Port separates Q1 2025 berth and yard occupancy from domestic crane effective-time and berth-time productivity
Brief / Confirmed

Makassar New Port: Test the Berth-Time Loss Before Committing Phase 1D

Makassar New Port entered its expanded operating phase with 1,280 m of quay and a reported 52 ha footprint at its February 2024 inauguration. Pelindo described Phase 1D as a further increment to be developed in response to demand. The subsequent operating records give an owner a practical starting point for that decision: the terminal's first-quarter 2025 berth occupancy was 28.49%, with yard occupancy of 39.61%. Pelindo's publication through August 2026 lists TPK New Makassar at 26.88 boxes per ship-hour gross for domestic containers. These dated measures support a closer examination of how existing berth time is used. [1][3][4]

Updated
Lach Huyen schematic separates the 375 m main berth, perpendicular 150 m barge wharf and parallel 50 m tug base, with dated full-load and partial-load ship cases
Brief / Confirmed

Lach Huyen: Planning a Partial-Load Call Across Three Wharves

HTIT welcomed MSC SPARKLE III and launched MSC's Pearl service on 9 October 2026. Behind that new service sits a conditional ship-size approval: Port of Hai Phong's 14 August 2025 account describes approval in principle for partially laden container ships of up to 165,000 DWT at berths 3 and 4. Its earlier April opening notice described berth 4 accepting 100,000-DWT ships fully laden. A planner needs the vessel's actual arrival condition alongside those dated operating records. [1][3][4]

Updated
Melaka mud-removal diagram shows the four boundary points in Port Circular 52/2026 and the two named anchor-handling tugs and two barges
Brief / Confirmed

Melaka sets a buoyed work area for power-plant mud removal

Malaysia's Marine Department has published a mud-removal work area for the Melaka 2,242 MW combined-cycle power plant, with a stated period from 7 October 2026 to 15 June 2027. Port Circular 52/2026, dated 12 October, identifies four boundary points and names anchor-handling tugs JETTA 35 and JETTA 37 and barges JETTA 39 and LIGHT SABER. It advises other vessels to keep clear of the work area and navigate cautiously nearby. [1]

Updated
Rach La engineering diagram shows the planned 55-metre channel, 148,619 cubic metres of dredging, one 320-metre-radius bend and 705 metres of bank protection in the Tay Ninh section.
Brief / Confirmed

Rach La's 55-Metre Channel Plan Carries a Shoreline Handover Condition

An October 2026 plan for Rach La canal in Tay Ninh specifies a 55-metre-wide navigation channel, 148,619 cubic metres of planned dredging and 705 metres of bank protection. It makes compensation and cleared-land handover part of the construction sequence.

Updated

Delivery network

Organizations active in this collection

6 shown / 62 profiled
IMWO illustrated guide to Boskalis' Dredging and Inland Infra, Offshore Energy, and Towage and Salvage businesses, separating corporate capabilities from individual project assignments
Dredging, marine infrastructure and offshore-energy contractor

Boskalis

Capital and maintenance dredging contractor / Port, waterway and reclamation contractor / Coastal defence, riverbank and hydraulic-infrastructure contractor

Corporate facts reviewed Procurement checked
Royal IHC-built cutter suction dredger Hussein Tantawy in Rotterdam before delivery to the Suez Canal Authority
Marine equipment provider

Royal IHC

Dredging vessel designer / Marine equipment manufacturer / Shipbuilder

Last checked
Cruise vessel M.V. Empress alongside Chennai Port with the harbour water and working quay visible
Indian major-port authority and east-coast public port owner

Chennai Port Authority

Statutory major-port authority / Chennai port owner and public infrastructure client / Navigation channel, berthing and marine traffic administrator

Last checked
Working Kandla cargo-berth line at Deendayal Port with bulk vessels, ship cranes and quay cranes
Indian major-port authority and Kandla public port owner

Deendayal Port Authority

Statutory major-port authority / Kandla port owner and public infrastructure client / Port planning, regulation and operations administrator

Last checked
Port of Apollo Bay harbour with its commercial fishing fleet, marina berths, wharf and breakwater
Victorian statutory coastal and local-port authority

Great Ocean Road Coast and Parks Authority

Statutory coast-and-parks manager / Port manager for Apollo Bay, Port Campbell and Lorne / Apollo Bay waterway manager and harbour-master function holder

Last checked
Aerial view across Geraldton Port showing operating commercial berths, cargo facilities and passenger vessels inside the harbour
Western Australian port authority and Government Trading Enterprise

Mid West Ports Authority

Geraldton Port and Fishing Boat Harbour operator / Port-reserve, berth, channel and marine-asset custodian / Geraldton Port Maximisation Project proponent and works client

Last checked

Continue the regional evidence review

Search the complete public index for this geography, compare the tracker records, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.

Search Asia Pacific Open project tracker Review methodology