Regional intelligence

Americas marine construction intelligence

Navigation upgrades, resilience schemes, industrial terminals, municipal waterfronts, and logistics-driven investment.

Projects, client activity, procurement and contractor appointments across Americas.

Latest item update 98 public projects 113 region-coded publications 49 active organizations
On this page

Current focus

Paraná export-waterway concession signed

Tracker coverage

98 project records connected to this region.

Publication coverage

113 current analyses and briefs coded to this region.

Organization coverage

49 public profiles identify active work or decision roles in this region.

Project coverage

All current Americas project records

98 records
Confirmed

Poplar Island dredged-material ecosystem restoration

United States / Dredged-material placement and intertidal marsh creation / Phased dredged-material placement and habitat development; published monitoring covers established marsh cells

construction / Last checked
Confirmed

United States Duke Marine Lab marsh-sill living shoreline

United States / Living shoreline sill and intertidal marsh / Restoration completed in 2002; NOAA reports stable sill geometry through a 2025 resurvey and long-term marsh monitoring.

completed / Last checked
Confirmed

Gulfport Harbor deep-draft navigation improvements

United States / Navigation-channel deepening and sedimentation basin / Signed Chief's recommendation dated 23 June 2026; Gulfport included in the House-passed September WRDA bill

planning / Last checked
Confirmed

West Point Dam spillway gates 1 and 2 maintenance

United States / Spillway-gate maintenance and reservoir operations / September 2026 owner plan schedules gate work and dam-road closure from 21 September to mid-January 2027

planning / Last checked
Confirmed

FY27 Galveston-area Scope Dredge to Budget

United States / Navigation channel maintenance dredging / 3 November presolicitation plans unrestricted firm-fixed-price maintenance dredging

planning / Last checked
Confirmed

Port of Progreso expansion dredging and north-platform procurement

Mexico / Dredging / ASIPONA records dredger arrival for third-phase stage 1 on 26 October 2026; estimated stage scope 3,076,370 m3. The July north-platform tender remains a separate historical procurement record.

construction / Last checked
Confirmed

Itajai 2026 channel maintenance dredging

Brazil / Navigation channel maintenance dredging / Daily Njord water injection reported; Utrecht return planned for November

construction / Last checked
Confirmed

Holt Lock permanent monolith repair

United States / Inland navigation lock rehabilitation and hydraulic steel structures / Permanent monolith repairs with revised navigation closures

construction / Last checked
Confirmed

New Haven Harbor improvement dredging

United States / Dredging and waterways / USACE DQM lists W912WJ26CA017 as active from 24 October 2026, naming Great Lakes and GL 58, GL 67 and GL 68.

construction / Last checked
Confirmed

Ocean City and Peck Beach 2026 Periodic Nourishment

United States / Coastal infrastructure / USACE records September 7 completion; the city reports 1.6 million cubic yards placed; New Jersey requested storm-repair assistance on October 16

completed / Last checked
Confirmed

Le Goulet Harbour 2026 maintenance dredging

Canada / Fishing harbour wharf, dredging and shore protection / CanadaBuys' 13 October data records the CAD 948,750 tax-inclusive Le Goulet contract CW2466490 awarded to Les Entreprises P E C inc on 10 September 2026; mobilisation, plant, dredged quantities and acceptance remain unreported

award / Last checked
Confirmed

Newark Bay FY26 federal navigation maintenance dredging

United States / Dredging and waterways / IFB W912DS26BA027 closed after the extended 6 August 2026 deadline; SAM lists the opportunity as inactive and publishes the bid abstract

tender / Last checked
Confirmed

Duwamish Waterway FY2026 maintenance dredging

United States / Navigation channel maintenance dredging / USACE awarded the USD 2.852 million contract to American Construction on 24 September 2026; dredging is scheduled no sooner than 1 December and mobilisation remains unreported

award / Last checked
Confirmed

Sandusky Harbor 2026 maintenance dredging and nearshore placement

United States / Navigation channel maintenance dredging / USACE scheduled Morrish-Wallace's 109,000-cubic-yard campaign to start on 6 October 2026 and finish by 1 November; actual mobilisation remains unverified

construction / Last checked
Confirmed

Brazos Island Harbor Phase 2 channel deepening

United States / Capital dredging and navigation-channel deepening / USACE lists Phase 2 in construction with new-work dredging continuing toward an FY2026 scheduled completion; final accepted depth, certified quantity and contract completion are unpublished

delivery / Last checked
Confirmed

Centreville small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Kerr Limited's CAD 18.86 million contract reached its amended 31 December 2025 expiry after 11 amendments; no cited owner record confirms accepted completion, final dredged quantities or reopening

delivery / Last checked
Confirmed

Hammond Cove Marina reconstruction

United States / Marinas, pontoons and berthing infrastructure / New York City's 22 January 2026 award notice names Empire Construction and Property Management Group at USD 4,583,648 for X310-117M; the city hazard plan identifies bulkhead, dock and electrical reconstruction, but no cited record establishes contract signing, notice to proceed, mobilisation or completion

award / Last checked
Confirmed

Port of Montreal Contrecœur Container Terminal

Canada / Port infrastructure / Site preparation under way; a quay-wall crane is installed and the owner recorded a 13-15 July sheet-pile delivery window, but the works log still does not evidence pile driving, dredger mobilisation, or accepted vessel access

construction / Last checked
Confirmed

Oswego Harbor 2026 breakwater repair phases

United States / Port infrastructure / USD 14.9 million phase-two award confirmed; construction planned from summer 2026 through 2028

award / Last checked
Confirmed

Wesleyville and Brookfield floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Granite Management received DFO contract 4500013526 on 23 December 2021 for a two-site floating-dock package; the 2021-22 Public Accounts mark the contract completed, while physical acceptance records remain unpublished

completed / Last checked
Confirmed

South Moose Lake 2025 harbour improvements

Canada / Remote fishing-harbour timber crib wharf and floating offloading dock / Fisheries and Oceans Canada awarded ZheMaak Inc. contract 4500091055 for CAD 220,542 on 8 August 2025; the published seven-month term ended on 27 March 2026, but the reviewed federal record does not publish physical completion, accepted quantities, owner handover or a final account

delivery / Last checked
Confirmed

Port de Grave marginal wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210731/001/PWD on 15 November 2021; CanadaBuys records a CAD 1,763,368 cumulative contract after amendments, and the 2022-23 Public Accounts mark the Port de Grave contract completed

completed / Last checked
Confirmed

Cap-aux-Meules access-channel dredging

Canada / Capital and maintenance dredging for a remote ferry, cargo and fishing port / PSPC awarded contract CW2402077 to Dragage Ocean DS on 1 September 2025; a CNESST filing places the contractor at the Cap-aux-Meules dredging site from a planned 13 October to 12 November 2025, while a 13 May 2026 amendment lifted the published contract total to CAD 6,724,266.72 without disclosing its scope

construction / Last checked
Confirmed

Winterton small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Maher's Contracting received F6140-210681/001/PWD on 22 October 2021; two CanadaBuys amendments raised the tax-inclusive contract to CAD 2.76 million, and the 2023-24 Public Accounts mark the Winterton contract completed

completed / Last checked
Confirmed

Edmonds North Portwalk Phase II electrification

United States / Marina electrical infrastructure, waterfront site preparation and public realm / The Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026

award / Last checked
Confirmed

Skinners Pond wharf 401 copewall rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Kildare Construction Ltd. received CAD 1.10 million contract 4500013345 on 23 December 2021 for structure 401; the 15 June 2022 target date is published, but completion and owner acceptance remain unverified

award / Last checked
Confirmed

Saint-Edouard-de-Kent containment-cell reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Christian Larocque Services LTEE received the CAD 347,878.45 construction contract in November 2021; Harbourside Engineering reports the rebuilt dredge-spoil containment cell completed in March 2022

completed / Last checked
Confirmed

Bellingham Shipping Terminal marine infrastructure and dredging

United States / Contaminated-sediment dredging, heavy-lift wharf replacement and terminal utilities / Port reporting confirms key dock and stormwater upgrades were completed in 2025 and navigation and environmental work advanced; Washington L&I records American Construction's contractor-reported 8 April 2026 work-completed date, but no filed Notice of Completion, owner acceptance, final hydrographic survey, final dredged quantity or final account is evidenced

delivery / Last checked
Confirmed

San Francisco Pier 80 mooring and berthing improvements

United States / Wharf maintenance, fender piles and marine asset renewal / The San Francisco Port Commission adopted Resolution 25-25 on 13 May 2025, authorizing award of Contract 2871 to Manson Construction Co. for USD 5,518,500 plus a USD 551,850 contingency; the cited official record does not confirm the planned notice to proceed, physical progress, substantial completion or acceptance

award / Last checked
Confirmed

Upper Mississippi Lock and Dam 9 miter-gate replacement

United States / Inland navigation lock rehabilitation and hydraulic steel structures / USACE reports that all four main-chamber miter gates were replaced in July 2026 by St. Paul and Rock Island District maintenance and repair crews; G&G Steel fabricated the gates in Alabama, while accepted installation cost, final account and post-installation performance remain unpublished

completed / Last checked
Confirmed

Petaluma River FY2025 maintenance dredging

United States / Port infrastructure / USACE records the FY2025 campaign complete after Dutra's USD 6.272 million dredging award; three reported subawards expose placement fees, DQM and survey support, tug setup and crew boats, while the final accepted quantity and account remain unpublished

completed / Last checked
Confirmed

Toledo Harbor 2026 maintenance dredging

United States / Port infrastructure / USD 5.3 million 2026 task order issued under a USD 11.1 million two-year Ryba contract; the September start remains planned

award / Last checked
Confirmed

Roberts Bank Terminal 2 landmass and wharf

Canada / Port infrastructure / TerraMarine is preferred proponent; contract negotiations, an in-progress Fisheries Act authorization and development work precede any target-price design-build agreement, financial close or mobilisation

design / Last checked
Confirmed

Dunkirk Harbor west breakwater rehabilitation

United States / Port infrastructure / Great Lakes Dock & Materials holds both phases; USACE reports the last 450 feet continuing through November 2026

construction / Last checked
Confirmed

Georgetown Harbor maintenance dredging

United States / Port infrastructure / Southern Dredging's Dredge BRUNSWICK is listed on active 24/7 work in the Bypass and Steel Mill channels through about 31 August 2026

construction / Last checked
Confirmed

Cheticamp Jobs Wharf floating-dock reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Superior Contracting's CAD 1.264 million contract ran from 14 October 2022 to 31 March 2023 for an integrated timber-wharf, dredging, breakwater, floating-dock and electrical package; the reviewed federal record does not publish accepted completion, measured quantities or final account

delivery / Last checked
Confirmed

Meteghan floating wharf and pile rehabilitation

Canada / Fishing harbour wharf, dredging and shore protection / Dexter holds CAD 4.29 million CW2462474 for floating-dock and pipe-pile replacement, while Connors Diving holds CAD 1.27 million 4500109325 for Wharf 403 pile jackets and concrete repairs; both awards are active but mobilisation and progress are unverified

award / Last checked
Confirmed

Glace Bay small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds CAD 8.90 million contract CW2454987 through 31 March 2027 for D1-D11 demolition and steel H-pile marginal-wharf reconstruction; award and scope are confirmed, while mobilisation and physical progress remain unverified

award / Last checked
Confirmed

Larrys River small craft harbour breakwater reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Zutphen Contractors holds active CAD 2.75 million contract CW2455209 through 27 November 2026 for rubble-mound breakwater construction at Larrys River; award and scope are confirmed but mobilisation and physical progress are not

delivery / Last checked
Confirmed

Grande-Anse harbour-basin dredging and containment-cell works

Canada / Fishing harbour wharf, dredging and shore protection / Les Entreprises P E C inc holds active CAD 862,270 contract CW2452382 through 31 December 2026 for barge-excavator dredging and containment-cell reconfiguration; earliest site start was 6 July and field progress remains unverified

delivery / Last checked
Confirmed

Sainte-Marie-Sur-Mer structure 401 wharf and breakwater works

Canada / Fishing harbour wharf, dredging and shore protection / L Breau and Sons Ltd holds active CAD 8.75 million contract CW2440554 through 24 August 2027 for structure 401 wharf reconstruction and a new breakwater; mobilisation, measured work and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Soubise/Marquis coastal protection: Soubise Lots 1 and 2

Grenada / Coastal infrastructure / Two Soubise works lots were signed on 27 April 2026 for a combined USD 5.747 million; Marquis Lot 3, notice to proceed, mobilisation and physical works remain publicly unconfirmed

award / Last checked
Confirmed

Bridgetown Fisheries Complex breakwater repair

Barbados / Coastal infrastructure / C. O. Williams' USD 8.482 million contract is confirmed and major armour works are in place; the public signing dates conflict and formal completion and owner acceptance remain unpublished

construction / Last checked
Confirmed

Tumaco port access-channel deepening, Phase I

Colombia / Capital dredging and navigation-channel deepening / SECOP II records contract GN2862-2026 signed with Consorcio Puerto Tumaco II for COP 26.826 billion and eight months, but the public ledger has no start date, invoicing or payment and the separate supervision procurement remains unawarded

award / Last checked
Confirmed

Barranquilla access-channel maintenance dredging

Colombia / Navigation channel maintenance dredging / SECOP II shows contract 0-525-2024 modified to COP 241.685 billion and 31 December 2026 after a 365-day extension; Cormagdalena reported 80.7% execution at 31 March before the later ledger update, while completion and acceptance remain unconfirmed

delivery / Last checked
Confirmed

Petit-Cap structure 403 wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Landco Construction's CAD 3.08 million contract ran from 2 November 2023 to 4 July 2024 for a Berlin-wall marginal wharf, harbour dredging and electrical reinstatement; CanadaBuys does not publish accepted completion or final quantities

delivery / Last checked
Confirmed

Harbour Grace small craft harbour wharf reconstruction

Canada / Fishing harbour wharf, dredging and shore protection / Bulldog Contracting received the CAD 7.05 million award on 1 April 2022 for timber-crib wharf, finger-pier, dredging and utility works; the reviewed federal record does not establish the delivery end date, accepted completion or final account

delivery / Last checked
Confirmed

Pugwash small craft harbour floating-dock works

Canada / Fishing harbour wharf, dredging and shore protection / Brian MacGillivary Construction's CAD 516,100 contract ran from 22 November 2023 to 29 March 2024; CanadaBuys confirms the award and amended term but publishes no accepted dredging quantity, dock handover or completion certificate

delivery / Last checked
Confirmed

Brazos Island Harbor FY24 entrance and jetty maintenance dredging

United States / Maintenance dredging and operating-port access / Great Lakes' Padre Island campaign was publicly scheduled from 20 October to 16 November 2024; an April 2025 final-quantity modification reduced the current federal obligation from USD 8.799 million to USD 7.456 million, while accepted quantities and formal closeout remain unpublished

delivery / Last checked
Confirmed

Sabine-Neches Contract 6 offshore channel deepening

United States / Dredging and waterways / Great Lakes holds the USD 219.108 million Contract 6 obligation; its USD 235.423 million potential value, April 2027 owner finish, production, assigned fleet and lower tiers remain to be confirmed

delivery / Last checked
Confirmed

Bridgetown Port Sugar Berth seawall and revetment repair

Barbados / Port infrastructure / World Bank contract record 1881500 names C. O. Williams Construction Limited at USD 3.338 million, but the public procurement chronology does not reconcile and no dated mobilisation, progress or completion record has been located

award / Last checked
Confirmed

Callao access-channel and inner-roadstead maintenance dredging

Peru / Maintenance dredging and operating-port access / APN started the access-channel and inner-roadstead campaign on 20 December 2025; a Jan De Nul post-dredging environmental report covers January 2026 monitoring, while owner acceptance, as-built hydrography and final account remain unverified

commissioning / Last checked
Confirmed

Moss Landing Harbor jetty repair and maintenance dredging

United States / Breakwater armour repair, access dredging and nearshore placement / Ahtna Infrastructure & Technologies held the USD 16,037,425 current-obligation contract for Moss Landing Harbor dredging and jetty repair; the US Coast Guard published 2025 field-work windows and USACE published August-September post-dredge surveys, but the 23 January 2026 contract end does not establish final quantity, jetty acceptance, completion or final account

construction / Last checked
Confirmed

Cap-des-Caissie small craft harbour upgrade

Canada / Fishing harbour wharf, dredging and shore protection / Mskikue'j Enterprises holds the CAD 5.09 million wharf and shore-protection contract through March 2027; the separate 2025 dredging and containment-cell contract reached its stated expiry without a public completion or measured-quantity record

award / Last checked
Confirmed

Arctic Bay Small Craft Harbour

Canada / Port infrastructure / Pilitak Enterprises holds the CAD 77.04m construction contract through 7 May 2030; DFO plans construction activity in 2026-27, while current public sources provide no marine mobilisation evidence

construction / Last checked
Confirmed

Port of Santos 16 m channel deepening

Brazil / Port infrastructure / Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead

award / Last checked
Confirmed

Saba Black Rocks Harbor and Fort Bay improvement works

Caribbean Netherlands / Hurricane-resilient harbor, breakwater, dredging, quay and marina works / Public Entity Saba reported steady construction progress on 10 May 2026, including breakwater works and Xbloc arrivals, with additional units being produced in Sint Eustatius. Dredging and excavation were active in March 2026, but marine completion, harbor handover, Fort Bay close-out and operational opening remain unconfirmed.

construction / Last checked
Confirmed

Puerto Antioquia multipurpose deep-water terminal

Colombia / Deep-water ports, dredging and multipurpose terminals / Commercial operations began on 5 February 2026 after four controlled vessel trials; the operator's current port-status ledger shows repeat container, breakbulk and refrigerated calls through July 2026

completed / Last checked
Confirmed

San Antonio Puerto Exterior common marine works

Chile / Deep-water ports, dredging and reclamation / Environmental approval was granted on 26 May 2026; six bidders or consortia are prequalified for the common marine-works tender, but no construction award has been announced

tender / Last checked
Confirmed

NOAA Newport MOC-P maintenance dredging

United States / Dredging / Six timely bids are publicly tabulated; no award, permit issuance, notice to proceed or mobilisation has been announced

evaluation / Last checked
Confirmed

Vermilion Harbor East Pier repair

United States / Port infrastructure / USACE officially completed the East Pier repair on 24 July 2026 after rebuilding 900 feet of the 1,333-foot structure

completed / Last checked
Confirmed

Niagara River Emerald Shiner Fish Passage

United States / Coastal infrastructure / USACE reports the 700-foot full phase completed in May 2026 and the combined 778-foot fish passage opened with a ribbon-cutting on 23 July 2026

completed / Last checked
Confirmed

Redwood City Channel FY26 maintenance dredging

United States / Dredging and waterways / HME Construction under contract; 24/7 clamshell dredging and dump-scow operations notified for July 2026

construction / Last checked
Confirmed

Snow's Cut AIWW shoreline stabilization

United States / Coastal infrastructure / USD 7.016 million contract awarded; mobilization and the awarded reach split remain unpublished

award / Last checked
Confirmed

Itajaí-Mirim flood-channel widening and dredging

Brazil / Dredging and waterways / World Bank project is Active and Board Approved; the April 2026 procurement plan omits the Itajaí-Mirim main works package

approval / Last checked
Confirmed

Port Mansfield Channel 2026 maintenance dredging

United States / Dredging and waterways / Callan Marine dredging has reached the Gulf Intracoastal Waterway junction; the Navigation District says the next work front is the harbor and turning basin

construction / Last checked
Confirmed

Richmond Inner Harbor FY26 maintenance dredging

United States / Port infrastructure / Updated full-and-open RFP issued 15 July 2026; proposals due 14 August 2026; no award or mobilisation recorded

tender / Last checked
Confirmed

Rosarito 2,200 l/s desalination procurement

Mexico / Marine utilities / Compras MX lists the invitation as current, with proposal opening deferred to 24 July 2026 and the ruling moved to 29 July; no award is published

tender / Last checked
Confirmed

Rocky River Harbor 2026 maintenance dredging

United States / Port infrastructure / Mechanical dredging began in late May 2026 and is scheduled to continue through August

construction / Last checked
Confirmed

Isle of Palms Breach Inlet beneficial-use dredging

United States / Coastal infrastructure / Two dredging packages completed on 27 February 2026; clay cleanup followed in April and staging was cleared in May

completed / Last checked
Confirmed

Sabine-Neches Waterway Channel Improvement Project

United States / Dredging and waterways / Callan Marine 44-foot package awarded; Great Lakes offshore Contract 6 in delivery; final 48-foot inland cut remains separate

construction / Last checked

Current research

Latest region-coded publications

6 shown / 113 current
USACE personnel inspecting Barkley's drained lock chamber beside exposed steel gate components and concrete walls in September 2026
Analysis / Lock Maintenance

Barkley: The Repair Window Runs Through Loaded Testing

Barkley's 2026 dewatering programme put miter-gate and valve repairs inside a planned 52-day navigation outage. USACE's 15 September account described a sequence extending from underwater clearance and chamber isolation through repairs, refilling and tests of miter-gate cycling and valve operation under hydraulic pressure. The work targeted miter gates and filling and emptying valves. Its September programme aimed to restore navigation on 1 October. A separate 2 October navigation notice identified Barkley as the diversion route for Kentucky Lock's planned 13-20 October closure. [1][2]

Updated
Miter-gate sections, a mobile crane and work platforms inside Chickamauga's new lock chamber on 20 February 2026, before the chamber-contract termination
Analysis / Contract Risk

Chickamauga: The $19 Million Adjustment After Termination

Chickamauga's lock-chamber termination changed Shimmick's reported revenue while the company contested the decision. The company disclosed a $19 million reduction in both revenue and cost of revenue in its results for the quarter ended 3 April 2026. Its subsequent-events note attributes the adjustment to the 8 May termination notice and previously estimated contract revenue. Shimmick disputes the termination and reported project claims still in process. [1]

Updated
Orange pipeline flotation collars beside dredged-material placement equipment at Poplar Island in March 2022
Brief / Confirmed

Poplar Island: Grading for the Marsh That Develops After Placement

At Poplar Island, the grading level helps determine how a constructed marsh develops after planting. A 2024 field study compared two areas of Cell 5AB with initial platform elevations of 0.22 m and 0.32 m NAVD88. Three surface elevation tables monitored each area. Mean elevation gains were 13.2 and 7.8 mm/year respectively over the study record through 2021. The lower area gained height faster; the higher area began with 0.10 m more elevation above the same datum. [1]

Updated
Duke Marine Lab living shoreline in a 2019 aerial photograph, showing the curved granite sill and established marsh on western Pivers Island
Brief / Confirmed

Duke Marine Lab: Quantifying a Living Shoreline's Elevation Deficit

Duke Marine Lab's living shoreline has retained its granite sill while the water around it has risen. NOAA's site report records consistent sill elevations between the post-construction survey and a 2025 resurvey. Its 2004-24 monitoring summary puts lower-marsh elevation gain at 2.0 mm/year and mid-marsh gain at 0.3 mm/year, against a local mean sea-level rise of 4.5 mm/year [1]. Those measurements describe different maintenance demands within one functioning coastal asset.

Updated
West Point Dam spillway operations, Georgia, 11 April 2025. Historical operating context.
Brief / Confirmed

West Point links gate maintenance to reservoir drawdown and dam-road closure

USACE's 2026 plan for maintenance and painting of West Point Dam spillway gates 1 and 2 combines reservoir drawdown with closure of Resource Management Drive across the dam. The 14 September notice scheduled work and road closure from 21 September, with maintenance expected to finish in mid-January 2027. Its reservoir target was 625 ft by 1 October; the notice leaves the elevation datum unspecified. The dam's technical sheet uses NGVD29. [1][2]

Updated
Gulfport funding diagram separates initial shares, later GNF repayment, local facilities and the estimated $17 million annual federal OMRR&R account, including maintenance dredging
Brief / Confirmed

Gulfport's deepening plan includes a later sponsor payment

Gulfport's recommended navigation improvements carry two different sponsor payments. The signed 23 June 2026 Chief's Report assigns $137.102 million of the $548.216 million initial project cost to the Mississippi State Port Authority. It also estimates an additional General Navigation Features payment at $50.8 million, before eligible credits. Paragraph 9(d) places that additional payment after construction, with interest, over a period of up to 30 years. A sponsor's funding forecast therefore needs a construction contribution and a separate post-completion repayment schedule. Annual federal operation, maintenance, repair, replacement and rehabilitation (OMRR&R) is estimated at $17 million, including anticipated maintenance dredging. [1]

Updated

Delivery network

Organizations active in this collection

6 shown / 49 profiled
American Construction Company floating crane, tug and marine construction plant working on a Seattle waterfront
Pacific Northwest marine construction and dredging contractor

American Construction Company

Navigational maintenance-dredging contractor / Environmental and contaminated-sediment dredging contractor / Open-water and contained material-placement contractor

Last checked
USACE hopper dredge Essayons operating in the Columbia River near Cathlamet, Washington
Federal water-resources agency and navigation-project owner

U.S. Army Corps of Engineers, Civil Works

Federal navigation project owner / Coastal and inland navigation asset manager / Planning, design, construction and operations-and-maintenance authority

Last checked
IMWO illustrated guide to Boskalis' Dredging and Inland Infra, Offshore Energy, and Towage and Salvage businesses, separating corporate capabilities from individual project assignments
Dredging, marine infrastructure and offshore-energy contractor

Boskalis

Capital and maintenance dredging contractor / Port, waterway and reclamation contractor / Coastal defence, riverbank and hydraulic-infrastructure contractor

Corporate facts reviewed Procurement checked
Royal IHC-built cutter suction dredger Hussein Tantawy in Rotterdam before delivery to the Suez Canal Authority
Marine equipment provider

Royal IHC

Dredging vessel designer / Marine equipment manufacturer / Shipbuilder

Last checked
Aerial view of Callan Marine cutter suction dredge General Bradley working beside a floating pipeline and coastal placement area
Dredging and marine construction contractor

Callan Marine

Capital and maintenance dredging contractor / Navigation-channel and berth dredging contractor / Beneficial-use and dredged-material placement contractor

Last checked
Aerial view of a tanker berth at Callao's mineral-concentrate and hydrocarbon terminal inside the breakwater, with port infrastructure and cranes beyond
Peruvian port authority and dredging client

Autoridad Portuaria Nacional (APN), Peru

National port planning / Port investment and technical review / Operations and environmental oversight

Last checked

Continue the regional evidence review

Search the complete public index for this geography, compare the tracker records, and use IMWO confidence labels before treating a signal as a tender, award, mobilisation, acceptance, or operating outcome.